# Frequently asked questions about purchases below the thresholds

- URL: https://procurelex.dk/en/faq/below-threshold
- Updated 2026-11-23
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-23
- Legal basis: section 10 of the Public Procurement Act, section 11 of the Public Procurement Act, section 191(1) of the Public Procurement Act, section 191(2) of the Public Procurement Act, section 192(1) of the Public Procurement Act, section 192(2) of the Public Procurement Act, section 192(3) of the Public Procurement Act, section 193(1) of the Public Procurement Act, section 193(2) of the Public Procurement Act, section 193(3) of the Public Procurement Act, section 193(4) of the Public Procurement Act, section 193(5) of the Public Procurement Act

Answers on advertising where there is a clear cross-border interest, market terms from DKK 500,000, documentation and the possibility of complaint for purchases below the EU thresholds.

Answers on purchases of supplies and services below the EU thresholds. For works below the threshold the Act on Calls for Tenders in the Construction Sector ([tilbudsloven](https://procurelex.dk/en/guides/danish-tender-act)) applies, which is not part of the Public Procurement Act (udbudsloven).

## Must I put a purchase below the threshold out to tender?

Not under the full rules of Part II. But purchases of supplies and services with a clear cross-border interest are covered by Part IV ([section 10 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/10)), and other purchases of at least DKK 500,000 excluding VAT by Part V ([section 11 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/11)). Below DKK 500,000, purchases of supplies and services are not covered by Parts II–V. See the [thresholds](https://procurelex.dk/en/thresholds).
## What is a clear cross-border interest?

The Act does not define it ([section 10 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/10)). It is a case-by-case assessment of whether the contract may interest undertakings in other EU countries, and the contracting authority should be able to justify its assessment. See the [guide on cross-border interest](https://procurelex.dk/en/guides/cross-border-interest).
## What does Part IV require of the contracting authority?

The contracting authority must advertise the contract before concluding it ([section 191(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/191#p1)), lay down an award procedure with award criteria ([section 192(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/192#p1)), inform potential tenderers of the procedure ([section 192(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/192#p2)) and notify all tenderers in writing and simultaneously of the award decision ([section 192(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/192#p3)).
## How do I ensure market terms under Part V?

For example by a market survey and one tender, by obtaining two or more tenders, or by advertising on the contracting authority's website ([section 193(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/193#p1)). The Act does not require a particular number of tenders, but the contracting authority must, to the extent necessary, be able to document that the purchase took place on market terms ([section 193(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/193#p4)).
## How many tenders may I obtain?

If you obtain more than three tenders, you must briefly state the reasons and inform the tenderers of the maximum number of tenders that will be obtained ([section 193(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/193#p2)).
## Must I notify those who did not win?

Yes. Under Part V, where you have received more than one tender, all tenderers must be notified simultaneously of the decision, and the reasons are given on request ([section 193(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/193#p3)). Under Part IV all tenderers must be notified in writing and simultaneously ([section 192(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/192#p3)).
## Can a tenderer complain to the Complaints Board for Public Procurement?

Under Part IV, yes: the time limit is 45 calendar days from the notification of the award, if it contains a statement of reasons ([section 7(4)(i) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p4-p1)). The Act on the Complaints Board does not apply to complaints about infringement of the Public Procurement Act's rule on market terms ([section 1(4) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/1#p4)), so Part V cannot be brought before the Board. See the [FAQ on remedies](https://procurelex.dk/en/faq/remedies).
## Which principles must I observe in a purchase under Part V?

The administrative-law principles of objectivity, sound financial management, the prohibition of extraneous considerations, equal treatment and proportionality ([section 193(5) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/193#p5)).