- Legal basis: section 6(1) of the Public Procurement Act, section 7 of the Public Procurement Act, section 8(1) of the Public Procurement Act, section 9 of the Public Procurement Act, section 10 of the Public Procurement Act, section 11 of the Public Procurement Act, section 29 of the Public Procurement Act, section 30(1) of the Public Procurement Act, section 30(2) of the Public Procurement Act, section 35 of the Public Procurement Act

Answers to the most common questions about the 2026–2027 EU thresholds, which part of the Public Procurement Act applies, and how the value of a contract is calculated.

These are answers to the questions contracting authorities and tenderers most often ask about the thresholds. All amounts exclude VAT.

## What are the thresholds for 2026–2027?

Works contracts: EUR 5,404,000 (DKK 40,313,840). Supplies and services: EUR 140,000 (DKK 1,044,400) for central government contracting authorities and EUR 216,000 (DKK 1,611,360) for other contracting authorities. Social and other specific services: EUR 750,000 (DKK 5,595,000). All amounts exclude VAT. See the [thresholds](https://procurelex.dk/en/thresholds) and the [guide](https://procurelex.dk/en/guides/thresholds).
## Why does the Public Procurement Act (udbudsloven) state different amounts?

The amounts in [section 6(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/6#p1) and [section 7 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/7) are those the Act was enacted with. The Commission revises the thresholds every second year, and contracting authorities must apply the thresholds in force at any given time ([section 9 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/9)). Always use the current amounts.
## Which part of the Act applies when the value is above the threshold?

Where the estimated value is equal to or greater than the threshold for the type of contract, Part II applies ([section 6(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/6#p1)). For social and other specific services in Annex XIV, the lighter regime of Part III applies instead where the value is equal to or greater than the threshold for them ([section 7 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/7)). See the [guide on social and specific services](https://procurelex.dk/en/guides/social-and-specific-services).
## What applies below the threshold?

Supply and service contracts with a clear cross-border interest are covered by Part IV ([section 10 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/10)). Other supply and service contracts of at least DKK 500,000 excluding VAT are covered by Part V ([section 11 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/11)). For works below the threshold the Act on Calls for Tenders in the Construction Sector ([tilbudsloven](https://procurelex.dk/en/guides/danish-tender-act)) applies, which is not part of the Public Procurement Act. See the [FAQ on below-threshold purchases](https://procurelex.dk/en/faq/below-threshold).
## When is the value calculated, and what must be included?

The value is the estimated value at the time of dispatch of the contract notice, or when the procedure is commenced if no notice is sent ([section 29 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/29)). It is calculated excluding VAT and includes all options and renewals ([section 30(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/30#p1)).
## May I split the purchase to stay below the threshold?

No. A contract may not be divided so that the procurement falls outside the Act unless this is objectively justified, and the calculation method may not be chosen to avoid the Act ([section 30(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/30#p2)). Recurrent purchases of the same kind often have to be added together ([section 35 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/35)). See the [guide on the value of the contract](https://procurelex.dk/en/guides/estimated-value).
## What if the contract is divided into lots?

The aggregate value of all the lots decides whether Part II or III applies, and the rules must be followed for each lot ([section 8(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/8#p1)). There is a narrow exception for small lots in [section 8(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/8#p2), but the monetary limits there are those of the Act as enacted and are revised together with the thresholds.