# Utilities Executive Order section 18

- URL: https://procurelex.dk/en/forsyningsvirksomhedsbekendtgoerelsen/18 · Dansk: https://procurelex.dk/da/forsyningsvirksomhedsbekendtgoerelsen/18
- Executive Order on the procedures for the award of contracts in the water, energy, transport and postal services sectors (Executive Order No. 1078 of 29 June 2022), consolidated version in force from 2022-07-01; official text (prevails): https://www.retsinformation.dk/eli/lta/2022/1078
- Procurelex's unofficial English translation, not yet reviewed by a lawyer. Only the Danish text is authentic: https://procurelex.dk/da/forsyningsvirksomhedsbekendtgoerelsen/18 · https://www.retsinformation.dk/eli/lta/2022/1078

Contracting entities may terminate a contract concluded under the Utilities Directive where
   1) the contract has been substantially modified, which would have required a new procurement procedure pursuant to Article 89,
   2) the supplier, at the time of the contract award, was in one of the situations referred to in sections 135-136 of the Public Procurement Act or, where relevant, section 137, and should therefore have been excluded from the procurement procedure pursuant to the second subparagraph of Article 80(1) of the Utilities Directive,
   3) the supplier, during the term of the contract or framework agreement, becomes subject to one of the grounds for exclusion in sections 135-137 of the Public Procurement Act and cannot demonstrate its reliability pursuant to section 138 of the Public Procurement Act, or
   4) the contract should not have been awarded to the supplier in view of a serious infringement of the obligations under the Treaties and this Directive that has been declared by the Court of Justice of the European Union in a procedure pursuant to Article 258 TFEU.