# Award criteria under the Public Procurement Act: price, cost and best price-quality ratio

- URL: https://procurelex.dk/en/guides/award-criteria
- Updated 2026-11-23
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-23
- Legal basis: section 159(1) of the Public Procurement Act, section 159(8) of the Public Procurement Act, section 160(1) of the Public Procurement Act, section 160(2) of the Public Procurement Act, section 161 of the Public Procurement Act, section 162(1) of the Public Procurement Act, section 162(3) of the Public Procurement Act, section 162(4) of the Public Procurement Act, section 163(1) of the Public Procurement Act, section 164(1) of the Public Procurement Act, section 165(1) of the Public Procurement Act, section 165(3) of the Public Procurement Act, section 166 of the Public Procurement Act, section 167 of the Public Procurement Act, section 168(1) of the Public Procurement Act

How the contracting authority identifies the most economically advantageous tender: the three award criteria, sub-criteria and weighting, the evaluation model and life-cycle costing.

The contracting authority must award the contract to the tenderer that has submitted the most economically advantageous tender ([section 161 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/161)). How that tender is found depends on the award criteria and the evaluation model the authority has described in the procurement documents. This guide goes through chapter 13 of the Public Procurement Act (udbudsloven) from the point of view of both the authority and the tenderer.

## The three award criteria

The contracting authority must identify the most economically advantageous tender on the basis of one of three award criteria ([section 162(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p1)):

- **Price** ([section 162(1)(i) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p1-p1)). The cheapest tender wins. There is nothing to weight, and the criterion suits uniform deliverables where quality is fixed by the specification.
- **Cost** ([section 162(1)(ii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p1-p2)). All forms of cost may be taken into account, including prices and life-cycle costs ([section 162(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p2)).
- **Best price-quality ratio** ([section 162(1)(iii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p1-p3)). The tender is assessed on price or cost and on qualitative sub-criteria.

The choice of criterion must be made before the procurement is carried out and must appear in the procurement documents. The authority cannot change it along the way.

## Sub-criteria and weighting

Under the best price-quality ratio, the tender is assessed on sub-criteria such as qualitative, environmental and social aspects ([section 162(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p3)). The Act gives these examples:

- quality, including technical merit, aesthetic and functional characteristics, accessibility, social, environmental and innovative characteristics ([section 162(3)(i) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p3-p1))
- the organisation, qualifications and experience of the staff assigned to perform the contract, but only where the quality of the staff can significantly affect the level of performance ([section 162(3)(ii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p3-p2))
- after-sales service, technical assistance and delivery conditions ([section 162(3)(iii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p3-p3)).

The authority may fix the price or the cost so that competition is on qualitative sub-criteria alone ([section 162(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/162#p4)).

Sub-criteria must be linked to the subject-matter of the contract ([section 163(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/163#p1)). They are, when they relate to the works, supplies or services to be provided, in any respect and at any stage of their life cycle, for example the production process, even where such factors are not part of the material substance of the purchase ([section 163(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/163#p2), [section 163(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/163#p3)).

The criteria must be transparent, must not give the authority an unrestricted freedom of choice between tenders, and must ensure effective competition. They must be accompanied by specifications that allow the information provided by tenderers to be verified effectively ([section 164(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/164#p1)).

The authority must state in the procurement documents how it will weight the sub-criteria. This does not apply where the assessment is on price or cost alone ([section 165(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/165#p1)). The weighting may be expressed as a range with a reasonable maximum spread ([section 165(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/165#p2)). Where weighting is not possible for objective reasons, the criteria must be listed in descending order of importance ([section 165(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/165#p3)).

## The evaluation model

The authority must lay down and describe in the procurement documents the content of every part of the evaluation model ([section 160(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/160#p1)). That covers how points or scores are given and how price and quality are converted and combined. Parameters of the model may depend on the tenders received, but only if it is unambiguously described in advance how they are fixed. They may not depend on the authority's choice or judgement after the tenders have been opened ([section 160(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/160#p1)).

An evaluation method described in accordance with this cannot be set aside by complaints bodies or courts if it is transparent and complies with the principle of equal treatment ([section 160(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/160#p2)). In practice, flaws in the model must be raised before the time limit for tenders expires, and the authority must apply the model as described.

The authority may examine the content of tenders only once the time limit has expired ([section 94 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/94)). Before award it must have verified that the tender meets the requirements of the procurement documents and that the tenderer is neither excluded nor lacking the required suitability ([section 159(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/159#p2)). In an open procedure the authority may choose to evaluate the tenders before verifying this ([section 159(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/159#p4)). Incomplete tenders may to a limited extent be supplemented or clarified, but not so that the tenderer in effect submits a new tender ([section 159(5) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/159#p5)). Where the procurement documents expressly state that a specific error leads to rejection, the tender must be rejected ([section 159(6) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/159#p6)).

## Life-cycle costing

Under the criteria cost and best price-quality ratio, the authority may take life-cycle costs into account ([section 166 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/166)). They may include costs of acquisition, use (such as energy consumption), maintenance and end-of-life ([section 166(i) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/166#pp1)), and costs of environmental externalities if their monetary value can be determined and verified ([section 166(ii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/166#pp2)).

If the authority assesses on life-cycle costs, the contract notice or the other procurement documents must state the data tenderers must provide and the method used to calculate the costs ([section 167 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/167)). A method for environmental externalities must be based on objectively verifiable and non-discriminatory criteria, must not unduly favour or disadvantage particular operators, must be accessible to all, and the data must be obtainable with reasonable effort ([section 168(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/168#p1)).

## Very large works contracts

In an open or restricted procedure for public works contracts with an estimated value above DKK 350 million excluding VAT, where the authority uses the best price-quality ratio, the qualitative criteria must be evaluated without knowledge of the evaluation of the price criterion ([section 159(8) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/159#p8)). The rule does not apply if the authority revokes its award decision ([section 159(9) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/159#p9), [section 170(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/170#p1)). The text of subsection 8 also provides that a particular provision of the Act on obtaining tenders in the construction sector (tilbudsloven) does not apply to such procurements. Tilbudsloven is not covered on this site.

## Practical tips

- Make the criteria and the model so precise that two evaluators would reach the same result.
- Choose only sub-criteria that are linked to the subject-matter of the contract and can be verified.
- If the model is unclear, ask while the time limit is running. After tender opening it will usually be binding.
- Tenders that seem unusually cheap are dealt with under the rules in the [guide on abnormally low tenders](https://procurelex.dk/en/guides/abnormally-low-tenders). What follows the evaluation is described in the [guide on award and standstill](https://procurelex.dk/en/guides/award-and-standstill).