# The Danish Tender Act (tilbudsloven): licitation and underhåndsbud for works below the threshold

- URL: https://procurelex.dk/en/guides/danish-tender-act
- Updated 2026-11-23
- Draft – awaiting legal review
- Legal basis: section 5 of the Public Procurement Act, section 6(1) of the Public Procurement Act, section 10 of the Public Procurement Act, section 11 of the Public Procurement Act, section 26(5) of the Public Procurement Act

What the Danish Tender Act requires when public builders and subsidised projects obtain tenders for works below the EU threshold: licitation, underhåndsbud, the DKK 300,000 and DKK 3 million limits, award, notification and complaints.

The rules of the Public Procurement Act (udbudsloven) for purchases below the thresholds, in Parts IV and V, apply only to supply and service contracts ([section 10 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/10), [section 11 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/11)). Works below the EU threshold are governed instead by the Danish Tender Act (tilbudsloven), the [Act on Calls for Tenders in the Construction Sector](https://www.retsinformation.dk/eli/lta/2007/1410). It decides whether tenders must be obtained through formal tendering (licitation) or may be obtained informally (underhåndsbud). The sections cited below are those of the Tender Act as amended up to 2022. The Act exists in Danish only; the English wording here is Procurelex's.

## Bill: the Tender Act to be repealed from 1 July 2027

On 7 October 2026 the Danish Government introduced a bill that repeals the Tender Act ([L 11, parliamentary year 2026-27](https://www.retsinformation.dk/eli/ft/202612L00011), section 3). Under the bill the Act is repealed on 1 July 2027. Works below the EU threshold worth DKK 500,000 or more excluding VAT would then be governed by Parts IV and V of the Public Procurement Act with a few additions, and licitation and underhåndsbud would no longer be required. Procurements launched before 1 July 2027 are completed under the rules in force until then, and complaints about them are dealt with under the same rules (section 4(5) and (6) of the bill).

The bill has not been adopted: on 23 November 2026 it has had its first reading in the Folketing and been referred to committee. Until a repeal is adopted and in force, the Tender Act applies as described below. This page will be updated once the Folketing has decided.

## When does the Tender Act apply?

The Act applies to obtaining tenders for the execution, or the design and execution, of works and to the award of the order (section 1(1)). It covers three groups of parties inviting tenders (udbydere) (section 1(2)):

1. central government, regional and local authorities and bodies governed by public law,
2. other parties, when they invite tenders for works that receive public support, including guarantees,
3. tenderers, when they obtain tenders from subcontractors for a task under the Act for a builder in group 1 or 2.

The Act does not apply to procurements covered by the Public Procurement Act, the Utilities Directive or the Act on municipalities' performance of tasks for other public authorities and municipalities' and regions' participation in companies, except for the tender validity period in section 3(2) and section 7 (section 1(3)). A public works contract that reaches the EU threshold is covered by Part II of the Public Procurement Act ([section 6(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/6#p1)). For 2026–2027 the threshold is EUR 5,404,000, or DKK 40,313,840 excluding VAT; see the [thresholds](https://procurelex.dk/en/thresholds).

The rules on the procedure and the award also apply where a party not covered by section 1(3) clearly states that the Act, or specified rules in it, will be used as the basis for the award (section 1(4)).

Mixed contracts with supplies or services under Part IV or V of the Public Procurement Act and works under the Tender Act follow the rules for their main subject-matter, with special rules for contracts that can be objectively separated ([section 26(5) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/26#p5)).

## Thresholds in the Tender Act: licitation or underhåndsbud

Tenders are obtained by open or restricted tendering (offentlig or begrænset licitation) or as informal tenders (underhåndsbud) (section 2(1)). The party inviting tenders must create sufficient competition and select tenderers on objective, relevant and non-discriminatory criteria (section 2(2) and (3)). For central government, regional and local authorities, the choice depends on the total estimated value of the works excluding VAT:

| Total estimated value excl. VAT               | What the Tender Act requires                                   | Tender Act                  |
| --------------------------------------------- | -------------------------------------------------------------- | --------------------------- |
| Up to DKK 300,000                             | Licitation or up to three underhåndsbud; no minimum number     | section 2(2), section 12(2) |
| Over DKK 300,000 and up to DKK 3 million      | Licitation or at least two and at most three underhåndsbud     | section 12(2) and (4)       |
| Over DKK 3 million and below the EU threshold | Licitation; underhåndsbud only in the exceptions the Act lists | section 12(3)               |
| The EU threshold and above                    | The Public Procurement Act                                     | section 1(3)                |

For bodies governed by public law and subsidised projects the minimum of two tenders also applies, but the cap of three tenders and the DKK 3 million limit are as a rule disapplied; see below.

## Informal tenders (underhåndsbud)

Tenders not obtained through licitation or on the basis of a framework agreement are underhåndsbud (section 12(1)).

- **At most three tenders.** The party inviting tenders may obtain up to three underhåndsbud for the same works, and a fourth if this was reserved in the invitations and the fourth is obtained from a tenderer outside the local area (section 12(2)).
- **At least two above DKK 300,000.** Above that value, parties in groups 1 and 2 must obtain at least two underhåndsbud and may not invite the same circle of undertakings every time (section 12(4)).
- **The award criterion** must be stated: lowest price or the most economically advantageous tender (section 12(5)).

**The DKK 3 million limit.** Parties in groups 1 and 2 may not obtain underhåndsbud for works worth more than DKK 3 million excluding VAT unless (section 12(3)):

1. the works are partial works of at most DKK 500,000 that together make up at most 20 per cent of the value of the works as a whole,
2. the extent, quality or timing of the works can only with great difficulty be laid down in tender documents, or the works cannot be postponed for compelling safety reasons,
3. a licitation produced no suitable or compliant tender or no requests to participate, and the original tender conditions are not substantially changed,
4. only one particular undertaking can carry out the works, or
5. the works supplement works put out to licitation, have become necessary because of unforeseen circumstances and are as a rule awarded to the undertaking carrying out the original works.

**Executive Order No 817 of 23 August 2005.** The Minister may exempt categories of parties from section 12(2) and (3) (section 12(7)). Under the [Executive Order on certain parties' use of underhåndsbud](https://www.retsinformation.dk/eli/lta/2005/817), the two rules do not apply to bodies governed by public law, nor to works with a commitment of public support, including guarantees or reimbursement of expenditure, unless the supporting authority has decided otherwise or the support is given under the Act on social housing (lov om almene boliger m.v.) or the legislation on urban renewal.

## Licitation: open and restricted

In a licitation, several parties are invited to submit binding tenders by the same time and on the same basis or on common minimum requirements, and it must be stated that the procedure is a licitation (section 4(1)).

- **Open tendering (offentlig licitation)** is addressed to an indefinite group by an advertisement in the press or in electronic media (section 4(2)). The advertisement states the award criterion and any requirements for evidence of technical and economic capacity (section 6(1)).
- **Restricted tendering (begrænset licitation)** is addressed directly to those from whom tenders are wanted (section 4(3)). With prequalification, the advertisement must state a time limit of at least 15 working days to express interest, the capacity requirements, the award criterion and the maximum number of bidders (section 6(2)). Without prequalification, the invitation states the maximum number of bidders and the award criterion, and parties in groups 1 and 2 must invite at least one bidder from outside the local area unless only certain undertakings are in practice able to carry out the works (section 6(3)).

Tenders must be in writing and may be submitted electronically unless the party inviting tenders has excluded it (section 5). The time limit for tenders must allow reasonable time (section 3(1)); the Act sets no minimum time limit for tenders. Tenders are opened at a time fixed in advance, and tenderers are entitled to learn the tender sums and any reservations immediately in connection with the opening (section 7a). The tender validity period is 40 working days unless the procurement documents state otherwise (section 3(2)).

## Award and negotiation

Unless the licitation is cancelled, the order is awarded on the lowest price or the most economically advantageous tender. The criterion must be in the tender conditions, and for the most economically advantageous tender the relative weighting of the criteria must as far as possible be stated, or otherwise their order of priority (section 8(1) and (2)). A tender may be rejected if it is more likely than not that the bidder cannot carry out the works to a satisfactory quality, in a sound manner and on time (section 8(3) and section 12(6)).

After a licitation, negotiation is possible. On lowest price, only with the lowest bidder (section 10). On the most economically advantageous tender, with three or fewer tenderers that submitted the most economically advantageous tenders under the weighted or prioritised sub-criteria, unless negotiation has been waived in the tender conditions (section 11(1)). All must be treated equally, and the negotiations may not substantially change the nature of the task or change the award criteria and their weighting (section 11(3) and (4)). A tenderer that is not invited, or is eliminated, is released from its tender as soon as it is told of the decision (section 3(3)).

A framework agreement under the Act can only be concluded between one party inviting tenders and one undertaking, for at most 4 years (section 13(2) and (3)).

## Notification

Everyone who submitted a tender in a licitation or an underhåndsbud must be notified as soon as possible of the award decision, including, where relevant, the reasons for cancelling a licitation or for obtaining underhåndsbud (section 14(1)). The reasons for rejecting a tender are given on request (section 14(3)). For the most economically advantageous tender, section 15 also governs information on the characteristics and relative advantages of the accepted tender.

## Persons in training and environmental and climate considerations

Since 1 July 2022, contracting authorities must include in the contract a requirement to use persons in training where the works contract is performed in Denmark, lasts at least 6 months from signature to delivery and has a value of at least DKK 5 million (section 7(1)). This does not apply where it entails a safety risk, is unsuitable for the contract or conflicts with other legislation (section 7(2)). The reference to section 7 in section 1(3) dates from before 2022, when section 7 dealt with the opening of tenders; the text does not settle how it is to be read today.

The Minister for Industry, Business and Financial Affairs may lay down rules requiring contracting authorities that do not take environmental or climate considerations into account to state the reasons in the procurement documents (section 16). Infringement may lead to a financial penalty or a fine ([section 13a of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/13a), [section 13b(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/13b#p1)).

## Complaints to the Complaints Board for Public Procurement

The Complaints Board for Public Procurement enforces the Tender Act ([section 1(2)(iv) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/1#p2-p4)). The time limit is 45 calendar days from the day after the notification of with whom the contracting authority has decided to enter into a contract, and 6 months for framework agreements, in both cases only if the notification contains reasons ([section 7(4) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p4)). A complaint of not having been prequalified must be lodged within 20 calendar days from the day after a notification with reasons was sent ([section 7(5) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p5)).

The Board may suspend the procedure, annul unlawful decisions, issue orders ([section 13(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/13#p1)) and award damages ([section 14(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/14#p1)). As worded, the standstill period and ineffectiveness apply only to Parts II and III of the Public Procurement Act and the Utilities Directive ([section 3(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/3#p1), [section 16 of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/16), [section 17(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/17#p1)), so a complaint has no automatic suspensive effect. The Board may grant suspensive effect where there are special reasons ([section 12(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/12#p1)). The right of access to the tenders under the Access to Public Administration Files Act is limited to those entitled to complain and to the mass media ([section 5 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/5)). See also the [guide on complaints](https://procurelex.dk/en/guides/remedies).

## The legal basis

The most recent consolidated act is [Consolidated Act No 1410 of 7 December 2007](https://www.retsinformation.dk/eli/lta/2007/1410). It must be read together with four amending acts:

- [Act No 618 of 14 June 2011](https://www.retsinformation.dk/eli/lta/2011/618), section 2: repealed the Act's own complaints rule.
- [Act No 1234 of 18 December 2012](https://www.retsinformation.dk/eli/lta/2012/1234), section 1: relaxed the advertising obligation for services in the then Part II.
- [Act No 1564 of 15 December 2015](https://www.retsinformation.dk/eli/lta/2015/1564) (the Public Procurement Act), section 198: gave the Act its current title and repealed Part II on supply and service contracts from 1 January 2016.
- [Act No 884 of 21 June 2022](https://www.retsinformation.dk/eli/lta/2022/884), section 3: introduced the requirement of persons in training in section 7, moved the opening of tenders to section 7a and inserted section 16, for procurements launched from 1 July 2022.

The Tender Act is not part of Procurelex's corpus; the official Danish text is on Retsinformation.

## What should you do?

1. [Calculate the total value of the works](https://procurelex.dk/en/guides/estimated-value). If it reaches the EU threshold, the Public Procurement Act applies.
2. Identify your group as a party inviting tenders, and check Executive Order No 817/2005.
3. Choose licitation or underhåndsbud according to the limits, and document any exception to the DKK 3 million limit.
4. State the award criterion before tenders are obtained, and notify all tenderers with reasons.