# Market consultation and preparing a procurement: preliminary market consultations and prior involvement

- URL: https://procurelex.dk/en/guides/market-consultation
- Updated 2026-11-23
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-23
- Legal basis: section 2(1) of the Public Procurement Act, section 4 of the Public Procurement Act, section 24(xviii) of the Public Procurement Act, section 39(1) of the Public Procurement Act, section 39(2) of the Public Procurement Act, section 39(3) of the Public Procurement Act, section 136(i) of the Public Procurement Act, section 136(ii) of the Public Procurement Act

What a contracting authority may do in dialogue with the market before a procurement is launched, and how distortion of competition caused by the prior involvement of an undertaking is prevented.

Before a contracting authority puts a procurement out to the market, it may need to find out what the market can deliver and what the requirements should contain. The Public Procurement Act (udbudsloven) allows the authority to talk to undertakings in advance, but it sets limits on how the dialogue may be used and on what must happen if an undertaking has influenced the design of the procurement.

## What a market consultation may be used for

Before launching a procurement procedure, a contracting authority may conduct market consultations to prepare the procurement and to inform economic operators of its plans and requirements. The authority may engage in dialogue with, and receive advice from, economic operators ([section 39(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/39#p1)).

The advice may be used in planning and conducting the procurement, but only if this does not breach the principles of equal treatment, transparency and proportionality ([section 2(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/2#p1)). A market consultation is therefore a tool, not an exception to the general principles.

In practice a market consultation can be used to clarify, for example:

- whether standard solutions exist or the need calls for a tailor-made solution
- which contract terms, delivery times and quality requirements are realistic
- whether it makes sense to [divide the contract into lots](https://procurelex.dk/en/guides/lots)
- how many undertakings, and which, can be expected to bid

The dialogue is preparation. It is not part of the procurement procedure itself and gives no undertaking a right to take part on particular terms.

## Where an undertaking has been involved

Where an economic operator or an undertaking related to an economic operator has advised the contracting authority in a market consultation, or has otherwise advised or been involved in preparing the procurement, the authority must take appropriate measures to prevent competition from being distorted by that operator's participation ([section 39(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/39#p2)). It makes no difference whether the advice was paid for, informal or simply part of a general consultation.

As a minimum, the authority must:

1. as far as possible ensure that relevant information exchanged with the undertaking during the preparation is included in the procurement documents ([section 39(2)(i) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/39#p2-p1)), and
2. fix the time limits for requests to participate and tenders so as to offset any time advantage the undertaking may have obtained ([section 39(2)(ii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/39#p2-p2)).

The first measure is about giving everyone the same information. If an undertaking has gained insight into the authority's operations, systems or plans that others do not have, that knowledge should be made available to all potential tenderers through the procurement documents. The second is about time: an undertaking that took part in the preparation has had longer to get ready, and the time limits must compensate for that. Minimum time limits are covered in the [guide on time limits](https://procurelex.dk/en/guides/time-limits).

## Exclusion as a last resort

Where the authority cannot ensure equal treatment by less intrusive measures, it must exclude the candidate or tenderer concerned ([section 39(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/39#p3)). The exclusion is made under the rule on distortion of competition arising from prior involvement ([section 136(ii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/136#pp2)), which the authority must be able to demonstrate.

Exclusion is therefore not a first step. The authority must first consider, and as a rule apply, the measures above. If the distortion of competition still cannot be remedied, there is no discretion: exclusion is mandatory. See also the [guide on grounds for exclusion](https://procurelex.dk/en/guides/exclusion-grounds).

For an undertaking this means that an early role in a project can cost it the chance to bid. That should be weighed before taking on advisory work that may later prevent participation. The undertaking should also bear in mind that advice on the requirements can come close to the requirements later imposed on tenderers.

## Conflicts of interest within the contracting authority

The Act also makes demands of the authority's own organisation. A contracting authority must take appropriate measures to prevent, identify and remedy conflicts of interest arising in the conduct of procurement ([section 4 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/4)).

A conflict of interest is a situation in which a person at the contracting authority, or at a procurement adviser acting on its behalf, who is involved in the procurement or may influence its outcome, has a direct or indirect financial, economic or other personal interest that might be perceived to compromise that person's impartiality and independence ([section 24(xviii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/24#pp18)). Where a conflict of interest cannot be effectively remedied by less intrusive measures, an affected candidate or tenderer must be excluded ([section 136(i) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/136#pp1)).

Practical measures include declarations of impartiality from staff and advisers, taking a person off the procurement, or reallocating tasks.

## Practical advice

- Plan the consultation in advance and decide who takes part and what is discussed.
- Document whom you have contacted, what information has been exchanged and which of it has been used in the procurement documents. The record is decisive if the procurement is later challenged.
- Use an open invitation to the market so that no undertaking is excluded from the dialogue.
- Assess early and concretely whether an undertaking's earlier involvement calls for compensating measures. Do not wait until tenders have been submitted.
- As an undertaking: tell the authority about any earlier advice, and be prepared for a longer time limit or for information to be shared with competitors.

See also the guides on [procurement documents](https://procurelex.dk/en/guides/procurement-documents) and [technical specifications](https://procurelex.dk/en/guides/technical-specifications), which a market consultation typically leads to.