# Procurement documents under the Public Procurement Act: content, access, questions and extending time limits

- URL: https://procurelex.dk/en/guides/procurement-documents
- Updated 2026-11-23
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-23
- Legal basis: section 5(2) of the Public Procurement Act, section 24(xxxvi) of the Public Procurement Act, section 93(1) of the Public Procurement Act, section 93(4) of the Public Procurement Act, section 128(1) of the Public Procurement Act, section 128(2) of the Public Procurement Act, section 128(3) of the Public Procurement Act, section 132(1) of the Public Procurement Act, section 132(2) of the Public Procurement Act, section 133 of the Public Procurement Act, section 134(1) of the Public Procurement Act, section 134(2) of the Public Procurement Act, section 134(3) of the Public Procurement Act

What the procurement documents comprise, how they are made available with the contract notice, how questions and modifications are handled, and when the time limit must be extended.

The procurement documents are the basis for every tender. What they say binds both the contracting authority and the tenderers, and it is what a complaint will be judged against. This guide covers what the documents comprise, how they are made available, and what applies to questions, modifications and extensions of time limits.

## What are the procurement documents?

Procurement documents are the documents which the contracting authority produces or refers to in order to describe or determine elements of the procurement, including ([section 24(xxxvi) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/24#pp36)):

- the contract notice
- the technical specifications
- the descriptive document
- proposed contract conditions
- formats for the presentation of documents by candidates and tenderers
- information on generally applicable obligations
- any additional documents

The list is not exhaustive. Everything the authority bases its assessment on should be in the documents so that tenderers know what they must meet. See [technical specifications](https://procurelex.dk/en/guides/technical-specifications), [lots](https://procurelex.dk/en/guides/lots) and [award criteria](https://procurelex.dk/en/guides/award-criteria).

## The contract notice

The authority must use a contract notice as a means of calling for competition in all procedures except the negotiated procedure without prior publication ([section 128(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/128#p1)). The notice must contain the information set out in Annex V, Part C, to Directive 2014/24/EU ([section 128(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/128#p2)), be drawn up in the Commission's standard forms, be sent electronically to the Publications Office of the European Union and be published in accordance with Annex VIII to the Directive ([section 128(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/128#p3)).

In an open procedure the notice must also state the time limit for receipt of tenders. In restricted procedures, competitive procedures with negotiation, competitive dialogues and innovation partnerships it states the time limit for requests to participate, while the time limit for tenders appears from the procurement documents ([section 93(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p3)). See the [guide on procedures](https://procurelex.dk/en/guides/procurement-procedures).

## Electronic access

The authority must offer unrestricted and full direct access free of charge by electronic means to the procurement documents from the date the contract notice is published in the Official Journal of the European Union, and must state in the notice the internet address at which they are accessible ([section 132(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/132#p1)).

The authority may refrain from offering open access to certain parts because of the special nature of the documents or for reasons of confidentiality ([section 132(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/132#p2)). It may impose confidentiality requirements on candidates and tenderers regarding the information made available ([section 5(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/5#p2)). Where parts are released only on request, the notice must state where and how access can be obtained.

Where not all the documents are available when the notice is published, the authority must extend the tender time limit by 5 days. There is no such obligation in case of urgency on the part of the authority ([section 133 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/133)).

## Additional information and modifications

Tenderers may have questions about the documents. The authority must communicate any additional information on the procurement documents and any additional documents no later than 6 days before the time limit expires ([section 134(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p2)). In open procedures, restricted procedures and competitive procedures with negotiation under the accelerated procedure the period is 4 days ([section 134(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p3)).

The authority may modify the procurement documents if ([section 134(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p1)):

1. the modifications are published in an appropriate manner ([section 134(1)(i) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p1-p1)),
2. notice is given within the time limits for additional information ([section 134(1)(ii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p1-p2)), and
3. the modifications do not alter fundamental elements ([section 134(1)(iii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p1-p3)).

The last condition is decisive. A change that could have affected who takes part, or distorted competition, cannot be made as a correction during an ongoing procedure ([section 24(xxxvii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/24#pp37)). The authority must then consider cancelling and re-tendering.

For equal treatment, answers to questions should go to everyone who has downloaded the documents, not only to the tenderer who asked. The authority should therefore use its electronic tendering system to publish questions and answers anonymously.

## Extending time limits

The authority must fix adequate time limits that at least comply with the minimum time limit for the procedure ([section 93(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p1)). It may extend the time limit for requests to participate or tenders, and is obliged to do so in these cases ([section 93(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4)):

| Situation                                                                                                   | Provision        |
| ----------------------------------------------------------------------------------------------------------- | ---------------- |
| additional information or documents are provided later than 6 days before the time limit                    | [section 93(4)(i) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4-p1) |
| substantial changes are made to the procurement documents                                                   | [section 93(4)(ii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4-p2) |
| documents without free electronic access are not sent within 5 days of a request                            | [section 93(4)(iii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4-p3) |
| the time limit was shortened for urgency and additional information is provided later than 4 days before it | [section 93(4)(iv) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4-p4) |

The Act does not say how long the extension must be. It should reflect how much time tenderers reasonably need to take the new information into account. Where substantial changes have been made, the extension should match their significance. See the [guide on time limits](https://procurelex.dk/en/guides/time-limits) and the [deadline calculator](https://procurelex.dk/en/deadlines).

## Practical advice

- Gather all requirements in the procurement documents. Requirements that appear only in oral answers or in unpublished annexes cannot be relied on.
- Answer questions in good time and extend the time limit if answers come late.
- As a tenderer: ask questions early and point out ambiguities before the time limit expires. See also the [guide on market consultation](https://procurelex.dk/en/guides/market-consultation) for the rules on preparation.