# Complaining to the Complaints Board for Public Procurement: time limits, suspension and sanctions

- URL: https://procurelex.dk/en/guides/remedies
- Updated 2026-11-23
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-23
- Legal basis: section 171(1) of the Public Procurement Act, section 171(4) of the Public Procurement Act, section 185(2) of the Public Procurement Act, section 195(1) of the Public Procurement Act, section 195(2) of the Public Procurement Act

How to challenge a procurement decision: who may complain, the time limits, the standstill period and suspensive effect, and what the Complaints Board for Public Procurement can do, from annulment and ineffectiveness to damages and financial penalties.

In Denmark, breaches of the procurement rules are enforced first and foremost by the Complaints Board for Public Procurement (Klagenævnet for Udbud). Anyone with a legal interest, or who is otherwise granted a right to complain under the Act on the Complaints Board for Public Procurement, may bring questions of infringement of the Public Procurement Act (udbudsloven) before the Board ([section 195(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/195#p1)). The time limits are short, and a complaint made during the standstill period can stop the contract, so it is important to know the rules before an award decision arrives.

## Who may complain?

A complaint may be lodged by anyone with a legal interest in the matter, by the Danish Competition and Consumer Authority, by organisations and authorities given a right to complain by the Minister for Industry, Business and Financial Affairs, and by corresponding organisations in other EU and EFTA states ([section 6(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/6#p1)). The Board may dismiss a complaint that is unsuitable as a basis for consideration ([section 6(2) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/6#p2)) and may allow a third party for whom the case is of material importance to intervene ([section 6(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/6#p3)).

At the latest when the complaint is lodged, the complainant must notify the contracting authority in writing that a complaint is being lodged and whether it is lodged within the standstill period. If it is not, the complainant must also state whether suspensive effect is requested ([section 6(4) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/6#p4)). Complaints about the award of contracts covered by Part V of the Act cannot be brought before the Board ([section 195(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/195#p2)).

## The standstill period and suspensive effect

Where a contracting authority decides to award a contract covered by Part II or III of the Act, it may conclude the contract only after a standstill period of 10 calendar days if the notification was sent electronically, or 15 calendar days if it was sent by letter, counted from the day after dispatch ([section 3(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/3#p1)). The authority may set a longer period ([section 3(2) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/3#p2)). Standstill does not apply to procedures without a prior contract notice, to contracts under framework agreements and dynamic purchasing systems, or where there is only one affected tenderer ([section 3(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/3#p3)). The notification must state when the period ends ([section 171(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/171#p4)). See also [award and standstill](https://procurelex.dk/en/guides/award-and-standstill).

A complaint lodged during the standstill period automatically has suspensive effect until the Board has decided whether the complaint should have suspensive effect until the final decision. The Board may grant suspensive effect only where special reasons so warrant, and must inform the authority of its decision within 30 calendar days of receiving the complaint ([section 12(2) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/12#p2), [section 12(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/12#p3)). A complaint lodged later does not automatically have suspensive effect, but the Board may, on request, grant it where special reasons so warrant ([section 12(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/12#p1)).

## Time limits

The time limit depends on what is challenged:

| What is challenged                                                                                                                   | Time limit                                                                             |
| ------------------------------------------------------------------------------------------------------------------------------------ | -------------------------------------------------------------------------------------- |
| Not being selected in a restricted procedure, competitive procedure with negotiation, competitive dialogue or innovation partnership | 20 calendar days from the day after the notification with reasons ([section 7(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p1))        |
| Other decisions and tenders, where the authority has published a notice that a contract has been concluded                           | 45 calendar days from the day after publication ([section 7(2)(i) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p2-p1))                       |
| Contract based on a framework agreement with reopening of competition, or a dynamic purchasing system                                | 30 calendar days from the day after notification with reasons ([section 7(2)(ii) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p2-p2))         |
| Framework agreement                                                                                                                  | 6 months from the day after the notification ([section 7(2)(iii) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p2-p3))                          |
| Decision to continue a contract after annulment                                                                                      | 20 calendar days ([section 7(2)(iv) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p2-p4))                                                      |
| Contract concluded without a contract notice, where the authority followed the procedure of announcing its intention in advance      | 30 calendar days from the day after the notice of the concluded contract ([section 7(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p3)) |

The Danish Competition and Consumer Authority may complain within 2 years of publication of the notice that the contract has been concluded ([section 7(7) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p7)). The time limits for the Tilbudsloven (the Act on obtaining tenders in the building and construction sector) and for certain provisions of udbudsloven that apply to some contracts below the thresholds appear in [section 7(4) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p4) and [section 7(5) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p5). Use the [deadline calculator](https://procurelex.dk/en/deadlines) to count the days.

## What can the Board do?

Where a contracting authority has infringed the rules, the Board may suspend the procedure, annul unlawful decisions or the whole tender, issue an order to bring the procedure into compliance, and impose a financial penalty ([section 13(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/13#p1)). Where a contract is declared ineffective, the Board orders the authority to terminate it ([section 13(2) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/13#p2)). The Board cannot award a party more than the party has claimed, and does not take into account matters the party has not invoked ([section 10(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/10#p1)).

### Ineffectiveness

A contract may be declared ineffective if it was concluded during the standstill period or while a complaint had suspensive effect ([section 16 of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/16)). It must be declared ineffective if the authority concluded it without a contract notice in breach of the rules ([section 17(1)(i) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/17#p1-p1)), or if it was concluded during standstill or suspension and the authority at the same time infringed the rules in a way that affected the complainant's chance of being awarded the contract ([section 17(1)(ii) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/17#p1-p2)). The same applies to certain unlawful contracts under framework agreements and dynamic purchasing systems above the threshold ([section 17(1)(iii) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/17#p1-p3), [section 17(1)(iv) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/17#p1-p4)). The contract may nevertheless be maintained where overriding reasons relating to a general interest require it ([section 17(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/17#p3)). In certain cases an authority can protect itself by first publishing a notice of its intention and waiting 10 calendar days ([section 4(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/4#p1)). Ineffectiveness applies only to future supplies ([section 18(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/18#p1)).

### Alternative penalties and financial penalty

Where a contract is not declared ineffective, or only in part, an alternative penalty is imposed ([section 18(2) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/18#p2)). For authorities that form part of public administration, this is a financial penalty, which can be imposed regardless of intent or negligence ([section 19(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/19#p1), [section 19(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/19#p3)). It must be paid to the Danish Competition and Consumer Authority within 8 weeks of the decision, unless the decision has been brought before the courts ([section 19(4) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/19#p4)). Other authorities are fined ([section 20(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/20#p1)). On the complainant's request, the Board also imposes on a public-administration authority a financial penalty of 1 per cent of the contract value, up to DKK 100,000, for failing to state the reasons for not dividing a contract into lots and for certain breaches of rules under the Tilbudsloven ([section 13a of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/13a)). Other authorities are fined for the same ([section 13b(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/13b#p1)).

### Damages

On request, the Board may order the contracting authority to pay damages for the loss the complainant has suffered as a result of an infringement ([section 14(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/14#p1)).

How the Board applies the rules shows in its decisions: see [the Complaints Board’s decisions](https://procurelex.dk/en/decisions), ordered by section of the Public Procurement Act, with a summary of each.

## Complaint fee and procedure

The Act authorises the Minister to lay down rules on a fee for lodging a complaint, on costs and on publication of decisions ([section 11(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/11#p3)). The amount of the fee does not appear in the text of the Act but in the rules issued under that authorisation, which must be consulted separately. Cases are as a rule prepared in writing ([section 11(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/11#p1)).

## The courts

A complaint made during the standstill period or while suspensive effect applies cannot be brought before the courts until the Board has decided ([section 5(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/5#p1)). The Board's decision may be brought before the courts no later than 8 weeks after it was communicated to the parties; after that it is final ([section 8(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/8#p1)). Cases against authorities that exploit a geographical area to explore for or extract oil, gas, coal or other solid fuel are brought before the Maritime and Commercial Court ([section 5(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/5#p3), [section 15(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/15#p1)). The time limits in [section 7 of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7) apply correspondingly where an action is brought before the courts without a prior complaint to the Board ([section 7(6) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/7#p6)).

## Practical advice

As a tenderer, review the award notification at once and decide whether there are grounds to complain before the standstill period ends. As a contracting authority, give full reasons and wait out the standstill period before concluding the contract. See also [contract modification](https://procurelex.dk/en/guides/contract-modification), which covers termination after an annulment.