# Time limits in a procurement: how they are counted, reduced and extended

- URL: https://procurelex.dk/en/guides/time-limits
- Updated 2026-11-23
- Reviewed by Mara Ribeiro Duarte (Head of Public Sector at Closer), 2026-11-23
- Legal basis: section 57(2) of the Public Procurement Act, section 57(3) of the Public Procurement Act, section 57(4) of the Public Procurement Act, section 57(5) of the Public Procurement Act, section 59(2) of the Public Procurement Act, section 60(2) of the Public Procurement Act, section 60(5) of the Public Procurement Act, section 63(2) of the Public Procurement Act, section 68(5) of the Public Procurement Act, section 74(5) of the Public Procurement Act, section 93 of the Public Procurement Act, section 94 of the Public Procurement Act, section 127(4) of the Public Procurement Act, section 134 of the Public Procurement Act, section 171(4) of the Public Procurement Act, section 173 of the Public Procurement Act

An overview of the minimum time limits for requests to participate and tenders in each procedure, when they may be reduced, and when they must be extended.

The Public Procurement Act (udbudsloven) sets minimum time limits that give candidates and tenderers time to apply and to tender. The contracting authority must fix an adequate time limit, which is at least the minimum for the chosen procedure ([section 93(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p1)). This guide covers the minimum periods, reduction and extension, additional information, and the periods that run after the award. Use the [deadline calculator](https://procurelex.dk/en/deadlines) to find the actual date.

## How the periods are counted

Where the Act sets a time limit in days, it generally runs from the day after dispatch: of the contract notice, or of the invitation to tender ([section 57(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/57#p2), [section 60(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/60#p2)). The day of dispatch itself is not counted. The starting point for the contract notice is the dispatch to the Publications Office of the EU, not the later publication. The standstill period is counted in calendar days from the day after the notice of the award decision is sent ([section 3(1)(i) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/3#p1-p1)).

## Minimum time limits by procedure

| Procedure                                       | Time limit              | Counted from                         |
| ----------------------------------------------- | ----------------------- | ------------------------------------ |
| Open procedure, tenders                         | 35 days ([section 57(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/57#p2)) | day after dispatch of the notice     |
| Restricted procedure, requests to participate   | 30 days ([section 59(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/59#p2)) | day after dispatch of the notice     |
| Restricted procedure, tenders                   | 30 days ([section 60(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/60#p2)) | day after dispatch of the invitation |
| Negotiated procedure, requests to participate   | 30 days ([section 63(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/63#p2)) | day after dispatch of the notice     |
| Negotiated procedure, initial tenders           | 30 days ([section 65(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/65#p2)) | day after dispatch of the invitation |
| Competitive dialogue, requests to participate   | 30 days ([section 68(5) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/68#p5)) | day after dispatch of the notice     |
| Innovation partnership, requests to participate | 30 days ([section 74(5) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/74#p5)) | day after dispatch of the notice     |
| Innovation partnership, initial tenders         | 30 days ([section 76(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/76#p2)) | day after dispatch of the invitation |

For final tenders in competitive dialogue, in the negotiated procedure and in the innovation partnership, the authority must fix an adequate time limit ([section 71(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/71#p2), [section 66(6) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/66#p6), [section 77(7) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/77#p7)), but the Act gives no minimum number of days. In the negotiated procedure without prior publication there is no notice and therefore no minimum time limit.

## Shortening the time limits

The Act provides three possibilities, which can to a large extent be combined with the rules for each procedure:

- **Prior information notice.** In the open procedure the time limit for tenders may be 15 days, and in the restricted procedure 10 days, if a prior information notice containing all the required information was sent for publication at least 35 days and at most 12 months before the contract notice was sent ([section 57(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/57#p3), [section 60(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/60#p3)). A prior information notice may cover at most 12 months ([section 127(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/127#p4)).
- **Electronic submission.** If the authority accepts electronic submission of tenders under the rules issued pursuant to [section 194(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/194#p1), the time limit for tenders in the open and restricted procedures may be reduced by 5 days ([section 57(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/57#p4), [section 60(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/60#p4)). The same applies to the innovation partnership ([section 76(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/76#p3)).
- **Urgency.** Where urgency on the part of the authority makes the minimum time limit impracticable, the time limit for tenders in the open procedure may not be shorter than 15 days ([section 57(5) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/57#p5)), for requests to participate in the restricted procedure 15 days ([section 59(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/59#p3)), and for tenders in the restricted procedure 10 days ([section 60(6) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/60#p6)). In the negotiated procedure the urgency possibility applies correspondingly to requests to participate ([section 63(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/63#p2)), and the possibilities of reduction after a prior information notice, electronic submission, an agreed time limit and urgency apply correspondingly to initial tenders ([section 65(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/65#p2)).

In the restricted procedure and the negotiated procedure, non-central government authorities may also agree the time limit for tenders with the selected candidates, provided all have the same time. It may not be less than 10 days from the day after the invitation is sent ([section 60(5) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/60#p5)). The same possibility exists in the innovation partnership ([section 76(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/76#p2)).

## Extending the time limit

The authority may extend the time limit for requests to participate or tenders. It must extend it if ([section 93(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4)):

1. additional information or documents are provided later than 6 days before the time limit ([section 93(4)(i) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4-p1)),
2. the procurement documents are materially changed ([section 93(4)(ii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4-p2)),
3. documents not made freely available by electronic means are not sent within 5 days of a request ([section 93(4)(iii) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4-p3)), or
4. the time limit was shortened for urgency and the information is provided later than 4 days before it ([section 93(4)(iv) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p4-p4)).

If tendering requires a site visit or inspection of documents at the authority, the time limit must be longer than the minimum so that tenderers can obtain the necessary information ([section 93(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p2)).

## Additional information and changes

The authority must provide additional information and documents no later than 6 days before the time limit expires ([section 134(2) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p2)); where the time limit was shortened for urgency, 4 days ([section 134(3) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p3)). Changes to the procurement documents must be published appropriately, notified within the same periods, and may not change fundamental elements ([section 134(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/134#p1)). The authority may examine applications and tenders only after the time limit has expired ([section 94 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/94)).

## After the award: standstill and notice

Once the authority has decided to award a contract, all affected candidates and tenderers must be notified, and the notification must state when the standstill period expires ([section 171(4) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/171#p4)). The contract may be concluded no earlier than the end of the standstill period ([section 173 of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/173)). The period is 10 calendar days from the day after dispatch if the notification was sent electronically, and 15 calendar days if sent by letter ([section 3(1) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/3#p1)). The authority may set a longer period ([section 3(2) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/3#p2)). The standstill period does not apply in the cases in [section 3(3) of the Complaints Board Act](https://procurelex.dk/en/klagenaevnsloven/3#p3), for example procurement without prior publication of a contract notice or an award under a framework agreement. A contract award notice must be sent to the Publications Office no later than 30 days after the contract is concluded ([section 129(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/129#p1)). See [award and standstill](https://procurelex.dk/en/guides/award-and-standstill).

## What to watch for

- Build in a buffer where the procurement documents are complex, even if the minimum is met. The time limit must be adequate, not merely lawful ([section 93(1) of the Public Procurement Act](https://procurelex.dk/en/udbudsloven/93#p1)).
- Answer questions early. A late answer may force you to postpone the time limit.
- Record the dispatch date, as it determines when the periods run.