(1) Where a contracting authority decides to award a contract which is covered by Part II or III of the Public Procurement Act or by the Utilities Directive, the contracting authority may not enter into the contract until a standstill period has expired of
   1) 10 calendar days counted from the day after the day on which the contracting authority sent the notification under section 2(1)(ii) or section 171(1)(iii) of the Public Procurement Act, if the notification was made by electronic means, or
   2) 15 calendar days counted from the day after the day on which the contracting authority sent the notification under section 2(1)(ii) or section 171(1)(iii) of the Public Procurement Act, if the notification was made by letter.
(2) A contracting authority may fix a longer standstill period than the periods referred to in subsection (1).
(3) Subsections (1) and (2) do not apply if
   1) a contract is awarded by a procurement procedure without prior publication of a contract notice,
   2) a contract is awarded to a supplier pursuant to a framework agreement with or without reopening of competition,
   3) a contract is awarded to a supplier within a dynamic purchasing system, or
   4) the only tenderer concerned is the tenderer to whom the contract is awarded, and there are no candidates concerned.