(1) A contracting authority may make modifications to the procurement documents where the following requirements are complied with:
   1) The modifications are published in an appropriate manner.
   2) Notice of the modification is given in compliance with the time limits for additional information, cf. subsections (2) and (3).
   3) The modifications do not constitute modifications of fundamental elements, cf. section 24(xxxvii).
(2) A contracting authority shall, no later than 6 days before the expiry of the time limit for the submission of requests to participate or tenders, communicate any additional information on the procurement documents and any additional documents, cf. however subsection (3).
(3) In open procedures, restricted procedures and competitive procedures with negotiation under the accelerated procedure, cf. section 57(5), section 59(3), section 60(6), section 63(2), cf. section 59(3), and section 65(2), cf. section 60(6), the contracting authority shall communicate additional information on the procurement documents and any additional documents no later than 4 days before the expiry of the time limit for the submission of requests to participate or tenders.