# Public Procurement Act section 136 – Mandatory grounds for exclusion

- URL: https://procurelex.dk/en/udbudsloven/136 · Dansk: https://procurelex.dk/da/udbudsloven/136
- Danish Public Procurement Act (udbudsloven) (Consolidated Act No. 116 of 3 February 2025), consolidated version in force from 2025-02-06; official text (prevails): https://www.retsinformation.dk/eli/lta/2025/116
- Procurelex's unofficial English translation, not yet reviewed by a lawyer. Only the Danish text is authentic: https://procurelex.dk/da/udbudsloven/136 · https://www.retsinformation.dk/eli/lta/2025/116

A contracting authority shall exclude a candidate or tenderer from participation in a procurement procedure where the contracting authority can demonstrate that
   1) a conflict of interest, cf. section 24(xviii), in relation to the procurement concerned cannot be effectively remedied by less intrusive measures,
   2) a distortion of competition as referred to in section 39, arising from the prior involvement of economic operators in the preparation of the procurement procedure, in relation to the procurement concerned cannot be remedied by less intrusive measures,
   3) the candidate or tenderer in the procurement concerned has seriously misrepresented information, has withheld information or is unable to submit supporting documents relating to the grounds for exclusion in section 135(1) or (3) and, where relevant, in section 137(1)(ii) or (vi), the minimum requirements of suitability laid down in sections 140-144 or the selection under section 145, or
   4) the candidate or tenderer has, in the course of its profession, committed grave professional misconduct which casts doubt on the integrity of the candidate or tenderer.