# Public Procurement Act section 155 – Evidence

- URL: https://procurelex.dk/en/udbudsloven/155 · Dansk: https://procurelex.dk/da/udbudsloven/155
- Danish Public Procurement Act (udbudsloven) (Consolidated Act No. 116 of 3 February 2025), consolidated version in force from 2025-02-06; official text (prevails): https://www.retsinformation.dk/eli/lta/2025/116
- Procurelex's unofficial English translation, not yet reviewed by a lawyer. Only the Danish text is authentic: https://procurelex.dk/da/udbudsloven/155 · https://www.retsinformation.dk/eli/lta/2025/116

A contracting authority may require the candidate or tenderer to provide evidence of its technical and professional ability. This shall be done in one or more of the following ways:
   1) A list of the works carried out over the past five years, accompanied by certificates of satisfactory execution and outcome for the most important works. Where necessary to ensure an adequate level of competition, the contracting authority may indicate that evidence of relevant works carried out more than five years before will also be taken into account.
   2) A list of the principal deliveries of supplies or services effected in the past three years, with the amounts, dates and public or private recipients. Where necessary to ensure an adequate level of competition, the contracting authority may indicate that evidence of relevant deliveries of supplies or services delivered or effected more than three years before will also be taken into account.
   3) Information about the technicians or technical bodies involved, especially those responsible for quality control, whether or not they belong directly or indirectly to the candidate's or tenderer's undertaking, and, in the case of public works contracts, information about the technicians or technical bodies which the contractor can call upon to carry out the work.
   4) A description of the technical facilities and the measures taken by the candidate or tenderer to ensure quality, and of the undertaking's study and research facilities.
   5) An indication of the supply chain management and tracking systems that the candidate or tenderer will be able to apply when performing the contract.
   6) A check carried out by the contracting authority or on its behalf by a competent official body of the country in which the supplier or service provider is established, subject to that body's consent, on the production capacities of the supplier or the technical and professional ability of the service provider and, where necessary, on the undertaking's study and research facilities and the quality control measures it will operate. This applies only where the supplies or services to be provided are complex or, exceptionally, are required for a special purpose.
   7) An indication of the educational and professional qualifications of the service provider or contractor or of the undertaking's managerial staff, provided that they are not evaluated as an award criterion.
   8) An indication of the environmental management measures that the candidate or tenderer will be able to apply when performing the contract.
   9) A statement of the service provider's or contractor's average annual manpower and the number of managerial staff for the last three years.
   10) A statement of the tools, plant or technical equipment available to the service provider or contractor for performing the contract.
   11) An indication of the proportion of the contract which the candidate or tenderer intends possibly to subcontract.
   12) As regards the supplies to be delivered:
      a) Samples, descriptions or photographs, the authenticity of which must be certifiable at the request of the contracting authority.
      b) Certificates drawn up by official quality control institutes or agencies of recognised competence attesting the conformity of supplies clearly identified by references to technical specifications or standards.