# Public Procurement Act section 159

- URL: https://procurelex.dk/en/udbudsloven/159 · Dansk: https://procurelex.dk/da/udbudsloven/159
- Danish Public Procurement Act (udbudsloven) (Consolidated Act No. 116 of 3 February 2025), consolidated version in force from 2025-02-06; official text (prevails): https://www.retsinformation.dk/eli/lta/2025/116
- Procurelex's unofficial English translation, not yet reviewed by a lawyer. Only the Danish text is authentic: https://procurelex.dk/da/udbudsloven/159 · https://www.retsinformation.dk/eli/lta/2025/116

(1) A contracting authority shall award the contract in accordance with sections 161-165 on the criteria for the award of the contract and, where relevant, sections 166-168 on the calculation of life-cycle costing and section 169 on abnormally low tenders.
(2) A contracting authority may award the contract only if it has verified that the tender complies with the requirements laid down in the contract notice and in the other procurement documents. The contracting authority shall, in addition, have verified, on the basis of the European Single Procurement Document, cf. sections 148-151, the evidence obtained pursuant to section 152(1), and e-Certis, cf. section 152(3), that the tender has been submitted by a tenderer
   1) that is not excluded under sections 135-137,
   2) that meets the minimum requirements of suitability laid down by the contracting authority under sections 140-143, and
   3) that, where relevant, has been selected to submit a tender through selection under section 145.
(3) In cases of doubt, the contracting authority shall carry out an effective check of the information and evidence in the request to participate or the tender.
(4) Where a contracting authority carries out an open procedure, it may choose to evaluate the tenders before verifying that the conditions in the first and second sentences of subsection (2), and subsection (2)(i)-(iii), are met.
(5) In compliance with the principles in section 2, the contracting authority may request the candidate or tenderer to supplement, clarify or complete the request to participate or the tender by submitting relevant information or evidence within an appropriate time limit, where the information or documents submitted by candidates or tenderers in connection with a request to participate or tender are incomplete or erroneous, or where specific documents are missing. The request may not lead the candidate or tenderer to submit a new request to participate or a new tender.
(6) Notwithstanding subsection (5), the contracting authority shall reject a request to participate or a tender where the procurement documents expressly state that a specific error or omission will lead to the request to participate or the tender being rejected, and the request to participate or tender in question contains such an error or omission.
(7) The contracting authority may decide not to award a contract put out to tender to the tenderer submitting the most economically advantageous tender where the contracting authority, after having heard the tenderer, can prove that the tender does not comply with applicable obligations in the fields of environmental, social and labour law under EU law, national legislation or collective agreements, or under the environmental, social and labour law obligations deriving from the conventions listed in Annex X to Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65).
(8) In open or restricted procedures for public works contracts with an estimated value of more than DKK 350 million excluding VAT, where the contracting authority applies the award criterion best price-quality ratio, cf. section 162(1)(iii), the contracting authority shall carry out the evaluation of the qualitative criteria without knowledge of the evaluation of the price criterion, cf. however subsection (9). When carrying out procurement covered by the first sentence, section 7 2) Section 7 of the Act on Calls for Tenders in the Construction Sector was restated by section 3 of Act no. 884 of 21 June 2022 amending the Public Procurement Act, the Act on the Complaints Board for Public Procurement and the Act on Calls for Tenders in the Construction Sector. By mistake, however, the reference to this section was not amended in connection with the amending act. of the Act on Calls for Tenders in the Construction Sector does not apply.
(9) Subsection (8) does not apply where the contracting authority withdraws its award decision under section 170.