# Public Procurement Act section 180 – Modification of contracts, etc.

- URL: https://procurelex.dk/en/udbudsloven/180 · Dansk: https://procurelex.dk/da/udbudsloven/180
- Danish Public Procurement Act (udbudsloven) (Consolidated Act No. 116 of 3 February 2025), consolidated version in force from 2025-02-06; official text (prevails): https://www.retsinformation.dk/eli/lta/2025/116
- Procurelex's unofficial English translation, not yet reviewed by a lawyer. Only the Danish text is authentic: https://procurelex.dk/da/udbudsloven/180 · https://www.retsinformation.dk/eli/lta/2025/116

(1) Modifications of a contract or framework agreement are not regarded as modifications of essential elements where the value of the modifications is below both
   1) the thresholds set out in section 6, and
   2) 10% of the value of the initial contract in the case of service and supply contracts, or below 15% of the value of the initial contract in the case of works contracts.
(2) Where several successive modifications are made to the same contract or framework agreement, the value of the modifications shall be aggregated in the calculation.
(3) Modifications pursuant to subsection (1) shall not, however, alter the overall nature of the contract or the framework agreement.