# Public Procurement Act section 181 – Modification of contracts, etc.

- URL: https://procurelex.dk/en/udbudsloven/181 · Dansk: https://procurelex.dk/da/udbudsloven/181
- Danish Public Procurement Act (udbudsloven) (Consolidated Act No. 116 of 3 February 2025), consolidated version in force from 2025-02-06; official text (prevails): https://www.retsinformation.dk/eli/lta/2025/116
- Procurelex's unofficial English translation, not yet reviewed by a lawyer. Only the Danish text is authentic: https://procurelex.dk/da/udbudsloven/181 · https://www.retsinformation.dk/eli/lta/2025/116

(1) Modifications concerning additional works, services or supplies by the original contractor are not regarded as modifications of essential elements of the contract where the modifications have become necessary for the performance of the contract and where a change of contractor
   1) cannot be made for economic or technical reasons, and
   2) would cause significant inconvenience or substantial duplication of costs for the contracting authority.
(2) The value of additional works, services or supplies shall not exceed 50% of the value of the initial contract.
(3) Where several successive modifications are made, the limitation in subsection (2) shall apply to the value of each modification.