(1) A contracting authority shall fix an adequate time limit for the receipt of tenders, cf. section 93.
(2) The time limit shall be a minimum of 35 days from the day following the dispatch of the contract notice.
(3) Where the contracting authority has used a prior information notice, the minimum time limit is, however, 15 days where
   1) the prior information notice contained all the information required in Annex V, Part B, Section I, to Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65), in so far as that information was available at the time of publication of the prior information notice, and
   2) the prior information notice was sent for publication not less than 35 days and not more than 12 months before the date of dispatch of the contract notice.
(4) Where the contracting authority accepts that tenders may be submitted by electronic means in accordance with rules issued by the Minister for Industry, Business and Financial Affairs pursuant to section 194(1), the time limit referred to in subsection (2) may be reduced by 5 days.
(5) Where a state of urgency duly substantiated by the contracting authority renders the time limit laid down in subsection (2) impracticable, the contracting authority may fix a time limit which shall not be shorter than 15 days from the day following the dispatch of the contract notice.
(6) The contracting authority shall publish the remaining procurement documents on the date of publication of the contract notice, cf. section 132.