# Public Procurement Act section 60 – Restricted procedure

- URL: https://procurelex.dk/en/udbudsloven/60 · Dansk: https://procurelex.dk/da/udbudsloven/60
- Danish Public Procurement Act (udbudsloven) (Consolidated Act No. 116 of 3 February 2025), consolidated version in force from 2025-02-06; official text (prevails): https://www.retsinformation.dk/eli/lta/2025/116
- Procurelex's unofficial English translation, not yet reviewed by a lawyer. Only the Danish text is authentic: https://procurelex.dk/da/udbudsloven/60 · https://www.retsinformation.dk/eli/lta/2025/116

(1) A contracting authority shall fix an adequate time limit for receipt of tenders, cf. section 93.
(2) The time limit shall be at least 30 days from the day after the invitation to submit a tender is sent.
(3) Where the contracting authority has used a prior information notice, the minimum time limit shall, however, be 10 days where
   1) the prior information notice contained all the information required in Annex V, Part B, Section I, to Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65), in so far as that information was available at the time of publication of the prior information notice, and
   2) the prior information notice was sent for publication at least 35 days and not more than 12 months before the date on which the contract notice was sent.
(4) Where the contracting authority accepts that tenders may be submitted by electronic means in accordance with rules issued by the Minister for Business and Growth pursuant to section 194(1), the time limit referred to in subsection (2) may be reduced by 5 days.
(5) Non-central government contracting authorities may fix the time limit for receipt of tenders by mutual agreement between the contracting authority and the selected candidates, provided that all selected candidates have the same time to prepare and submit tenders. The time limit for receipt of tenders shall, however, be at least 10 days from the day after the invitation to submit a tender is sent.
(6) Where a state of urgency on the part of the contracting authority renders it impossible to comply with the time limit referred to in subsection (2), the contracting authority may fix a time limit for receipt of tenders that is not less than 10 days from the day after the invitation to submit a tender is sent.