# Public Procurement Act section 80 – Negotiated procedure without prior publication

- URL: https://procurelex.dk/en/udbudsloven/80 · Dansk: https://procurelex.dk/da/udbudsloven/80
- Danish Public Procurement Act (udbudsloven) (Consolidated Act No. 116 of 3 February 2025), consolidated version in force from 2025-02-06; official text (prevails): https://www.retsinformation.dk/eli/lta/2025/116
- Procurelex's unofficial English translation, not yet reviewed by a lawyer. Only the Danish text is authentic: https://procurelex.dk/da/udbudsloven/80 · https://www.retsinformation.dk/eli/lta/2025/116

(1) A contracting authority may use the negotiated procedure without prior publication where, in connection with an open or restricted procedure for public works contracts, public supply contracts and public service contracts,
   1) no requests to participate or tenders have been received, or
   2) only requests to participate or tenders that are irrelevant to the contract have been received.
(2) It is a condition under subsection (1) that the fundamental elements of the original procurement documents are not substantially altered and that a report is sent to the European Commission if it so requests.
(3) A contracting authority may also use the negotiated procedure without prior publication where the works, supplies or services can be supplied only by a particular economic operator for any of the following reasons:
   1) the aim of the procurement is the creation or acquisition of a unique work of art or artistic performance,
   2) absence of competition for technical reasons, or
   3) the protection of exclusive rights, including intellectual property rights.
(4) Paragraphs (ii) and (iii) of subsection (3) apply only where no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters of the procurement.
(5) A contracting authority may also use the negotiated procedure without prior publication, in so far as is strictly necessary, where, for reasons of extreme urgency brought about by events unforeseeable by the contracting authority, the time limits for open procedures, restricted procedures or competitive procedures with negotiation cannot be complied with.