(1) A contracting authority shall fix adequate time limits for the submission of requests to participate and tenders. The time limit for receipt of tenders and requests to participate shall, as a minimum, comply with the minimum time limit for the procurement procedure concerned.
(2) Where tenders can be submitted only after a visit to the site or after on-the-spot inspection of the documents supporting the procurement documents at the premises of the contracting authority, the contracting authority shall fix a time limit for receipt of tenders such that all tenderers may be aware of all the information needed to prepare a tender. The time limit shall be longer than the minimum time limit indicated for the procurement procedure concerned.
(3) In open procedures, the contracting authority shall state the time limit for receipt of tenders in the contract notice. In restricted procedures, competitive procedures with negotiation, competitive dialogues and innovation partnerships, the contracting authority shall state the time limit for receipt of requests to participate in the contract notice, and the time limit for receipt of tenders shall appear from the procurement documents.
(4) A contracting authority may extend the time limit for receipt of requests to participate or tenders. The contracting authority is obliged to extend the time limit for receipt of requests to participate or tenders in the following cases:
   1) Where the contracting authority provides additional information concerning the procurement documents or additional documents later than 6 days before the time limit fixed for receipt of requests to participate or tenders.
   2) Where the contracting authority makes substantial changes to the procurement documents.
   3) Where the contracting authority does not, within 5 days of a request to that effect, send the documents to which free, direct and full electronic access has not been offered, cf. section 132(2).
   4) Where the contracting authority has shortened the time limit because of an urgency on the part of the contracting authority, cf. section 57(5), section 59(3) and section 65(2), cf. section 60(6), and the contracting authority provides additional information concerning the procurement documents or additional documents later than 4 days before the time limit fixed for receipt of requests to participate or tenders.