The EU thresholds applying for 2026–2027 in euro and kroner, and which part of the Public Procurement Act (udbudsloven) comes into play depending on the value and type of the contract.

Updated 23 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 23 November 2026

Legal basissection 6(1) · section 6(3) · section 7 · section 8(1) · section 8(2) · section 9 · section 10 · section 11 · section 29 · section 30(1) · section 186 · section 191(1) · section 193(1) · official text

The thresholds decide how strict the Public Procurement Act (udbudsloven) is for a given purchase. Above them the full EU procurement rules of Part II apply. Below them lighter rules apply, and for the smallest purchases the requirements are limited. This guide gives the current amounts for 2026–2027 and an overview of which part applies when. The overall picture of the thresholds is on the page of the same name.

The thresholds for 2026–2027

The thresholds are set in EU law and revised by the European Commission every second year. Contracting authorities must apply the thresholds in force at any given time (section 9 of the Public Procurement Act). For 2026–2027 the amounts follow from Delegated Regulations (EU) 2025/2150, 2025/2151 and 2025/2152, and the kroner amounts from the Commission communication C/2025/5732. All amounts exclude VAT.

Type of contractEURDKK
Works contracts5,404,00040,313,840
Supplies and services, central government contracting authorities140,0001,044,400
Supplies and services, other contracting authorities216,0001,611,360
Social and other specific services (Part III)750,0005,595,000

Utilities and concessions have their own thresholds (utilities: EUR 432,000 for supplies and services, EUR 5,404,000 for works and EUR 1,000,000 for social services; concessions: EUR 5,404,000). They are covered in the guide on utilities and concessions.

Note that the amounts printed in the Act itself are out of date. The Act states kroner amounts in section 6(1) of the Public Procurement Act, section 7 of the Public Procurement Act and section 8(2) of the Public Procurement Act, but these are the amounts of the Act as first enacted. For example, DKK 38,624,809 is stated for works in section 6(1)(i) of the Public Procurement Act. The Act's own rule is that the Commission revises the thresholds every second year and that the thresholds in force at any given time are the ones to apply (section 9 of the Public Procurement Act). Never rely on the text of the Act alone to decide whether a contract is above a threshold.

Which part applies when?

Part II: the full rules. Part II applies where the estimated value of the contract is equal to or greater than the threshold for that type of contract (section 6(1) of the Public Procurement Act). This is where the rules on procedures, time limits, exclusion, award and standstill are found. Part II also applies to certain contracts that are not public contracts, namely works and related services to which the contracting authority provides a direct subsidy of more than 50 per cent (section 6(3) of the Public Procurement Act).

Part III: social and other specific services. Part III applies to the services listed in Annex XIV to the Procurement Directive (including health, social and cultural services) where the value is equal to or greater than the threshold for them (section 7 of the Public Procurement Act). The rules are lighter than in Part II; see the guide on social and other specific services.

Part IV: below the threshold, but with a clear cross-border interest. Part IV applies to supply and service contracts not covered by Part II or III if the contract has a clear cross-border interest (section 10 of the Public Procurement Act). The contracting authority must then advertise the contract (section 191(1) of the Public Procurement Act). See the guide on clear cross-border interest.

Part V: supply and service contracts from DKK 500,000. Part V applies to supply and service contracts not covered by Parts II–IV that have an estimated value of at least DKK 500,000 excluding VAT (section 11 of the Public Procurement Act). The contracting authority must ensure that the purchase takes place on market terms (section 193(1) of the Public Procurement Act). This amount is not an EU threshold and is not revised by the Commission.

Below DKK 500,000, and works below the threshold. Supply and service contracts below DKK 500,000 are not covered by Parts II–V. Nor does the Act contain a part for works contracts below the threshold. For them the Act on Calls for Tenders in the Construction Sector (tilbudsloven) applies, which is not part of the Public Procurement Act and must be consulted separately.

Lots

Where works, services or the purchase of similar supplies are divided into lots, Part II or III applies to each lot if the aggregate value of all the lots reaches the threshold (section 8(1) of the Public Procurement Act). There is a narrow exception: the contracting authority may award a lot without applying Part II or III if the value of the lot is below DKK 596,408 (supplies and services) or DKK 7,455,100 (works), and the lots awarded in that way together make up no more than 20 per cent of the aggregate value (section 8(2) of the Public Procurement Act). These amounts are again those the Act was enacted with, and they are revised together with the thresholds (section 9 of the Public Procurement Act), so check the amounts in force before relying on the exception. See the guide on calculating the estimated value.

Using the thresholds in practice

  1. Calculate the value first. What counts is the estimated value at the time the contract notice is sent. If no notice is sent, it is the time when the procedure is commenced (section 29 of the Public Procurement Act). The value is calculated excluding VAT and includes options and renewals (section 30(1) of the Public Procurement Act).
  2. Identify the type of contracting authority. Central government contracting authorities have a lower threshold for supplies and services than other authorities.
  3. Check which threshold applies now. Use the current amounts, not those in the text of the Act.
  4. Choose the part. Above the threshold: Part II (or III). Below it: assess cross-border interest (Part IV), otherwise Part V from DKK 500,000.

The value may not be set or split in order to keep a purchase below a threshold (section 30(2) of the Public Procurement Act).