Time limits
Public procurement time limits under the Public Procurement Act
The time limits of the Public Procurement Act and of the Complaints Board Act for tenders, requests to participate, clarification, standstill, notices and complaints, each with the provision it is read from, and a calculator that counts the end of a period.
Count a time limit
Choose a time limit and the date of the act it runs from (the dispatch of the notice, for example). The count shows the first and the last day counted and the end of the period.
A draft aid, not legal advice: the counting rule has not been reviewed by a lawyer. Check the date against the provision and the facts of your procedure.
How the days are counted here
- The Acts count from the day after the act a period runs from («fra dagen efter»), as Regulation (EEC, Euratom) No 1182/71 does for the EU procurement directives (Article 3(1)).
- A period in days counts Saturdays, Sundays and public holidays; a period in working days counts working days only; a period in months ends on the day of the last month with the same number.
- If the last day of the period is a Saturday, a Sunday or a public holiday, the period ends at the end of the next working day (Article 3(4) of Regulation 1182/71); this does not apply to a period counted backwards from a date.
That Regulation 1182/71 governs the counting of these time limits is our reading; a lawyer has not yet reviewed it.
Open procedure
| Time limit | What | Counted from | Legal basis |
|---|---|---|---|
| 35 daysminimum | Time limit for tenders in the open procedure | the day after the dispatch of the contract notice | section 57(2) of the Public Procurement Act |
| 15 daysminimum | Shortened time limit after a prior information notice | the day after the dispatch of the contract notice | section 57(3) of the Public Procurement Act |
| 5 daysshorter by | Reduction where tenders may be submitted electronically | — | section 57(4) of the Public Procurement Act |
| 15 daysminimum | Time limit in a state of urgency (accelerated procedure) | the day after the dispatch of the contract notice | section 57(5) of the Public Procurement Act |
Restricted procedure
| Time limit | What | Counted from | Legal basis |
|---|---|---|---|
| 30 daysminimum | Time limit for requests to participate in the restricted procedure | the day after the dispatch of the contract notice | section 59(2) of the Public Procurement Act |
| 15 daysminimum | Time limit for requests to participate in a state of urgency | the day after the dispatch of the contract notice | section 59(3) of the Public Procurement Act |
| 30 daysminimum | Time limit for tenders in the restricted procedure | the day after the dispatch of the invitation to tender | section 60(2) of the Public Procurement Act |
| 10 daysminimum | Shortened time limit for tenders after a prior information notice | the day after the dispatch of the invitation to tender | section 60(3) of the Public Procurement Act |
| 5 daysshorter by | Reduction where tenders may be submitted electronically | — | section 60(4) of the Public Procurement Act |
| 10 daysminimum | Time limit for tenders in a state of urgency | the day after the dispatch of the invitation to tender | section 60(6) of the Public Procurement Act |
Negotiation, dialogue, innovation partnership and dynamic purchasing
| Time limit | What | Counted from | Legal basis |
|---|---|---|---|
| 30 daysminimum | Time limit for requests to participate in the competitive procedure with negotiation | the day after the dispatch of the contract notice | section 63(2) of the Public Procurement Act |
| 30 daysminimum | Time limit for initial tenders in the competitive procedure with negotiation | the day after the dispatch of the invitation to tender | section 65(2) of the Public Procurement Act |
| 30 daysminimum | Time limit for requests to participate in the competitive dialogue | the day after the dispatch of the contract notice | section 68(5) of the Public Procurement Act |
| 30 daysminimum | Time limit for requests to participate in an innovation partnership | the day after the dispatch of the contract notice | section 74(5) of the Public Procurement Act |
| 30 daysminimum | Time limit for requests to participate when a dynamic purchasing system is set up | the day after the dispatch of the contract notice | section 104(1) of the Public Procurement Act |
| 10 daysminimum | Time limit for tenders for a specific purchase in a dynamic purchasing system | the day after the dispatch of the invitation to tender | section 105(4) of the Public Procurement Act |
| 10 working daysmaximum | Assessment of a request to join a dynamic purchasing system | receipt of the request | section 104(4) of the Public Procurement Act |
Below the thresholds: complaints
| Time limit | What | Counted from | Legal basis |
|---|---|---|---|
| 45 daysmaximum | Complaint under the Tender Act or sections 191-192 of the Public Procurement Act | the day after the notification | section 7(4)(i) of the Complaints Board Act |
| 20 daysmaximum | Complaint about not being prequalified (below the thresholds) | the day after the notification is sent | section 7(5) of the Complaints Board Act |
Clarification, auctions and standstill
| Time limit | What | Counted from | Legal basis |
|---|---|---|---|
| 2 working daysminimum | Earliest start of an electronic auction | the dispatch of the invitation | section 113(1) of the Public Procurement Act |
| 6 daysminimum | Supplementary information on the procurement documents | the expiry of the time limit for requests or tenders | section 134(2) of the Public Procurement Act |
| 5 dayslonger by | Extension where the procurement documents are not available on publication | — | section 133 of the Public Procurement Act |
| 10 daysminimum | Standstill period after electronic notification | the day after the notification is sent | section 3(1)(i) of the Complaints Board Act |
| 15 daysminimum | Standstill period after notification by letter | the day after the notification is sent | section 3(1)(ii) of the Complaints Board Act |
Notices and publication
| Time limit | What | Counted from | Legal basis |
|---|---|---|---|
| 30 daysmaximum | Contract award notice | the conclusion of the contract | section 129(1) of the Public Procurement Act |
Complaints to the Complaints Board
| Time limit | What | Counted from | Legal basis |
|---|---|---|---|
| 20 daysmaximum | Complaint about not being selected | the day after the notification is sent | section 7(1) of the Complaints Board Act |
| 45 daysmaximum | Complaint after a published contract award notice | the day after publication | section 7(2)(i) of the Complaints Board Act |
| 30 daysmaximum | Complaint about a call-off after reopened competition or in a dynamic purchasing system | the day after the notification | section 7(2)(ii) of the Complaints Board Act |
| 6 monthsmaximum | Complaint about a framework agreement concluded | the day after the notification | section 7(2)(iii) of the Complaints Board Act |
| 30 daysmaximum | Complaint after a voluntary ex ante transparency notice | the day after publication | section 7(3) of the Complaints Board Act |
Public holidays in 2026
The holidays of the national church; store bededag is no longer a public holiday from 2024. Saturdays and Sundays are not working days either.
- 1 January 2026New Year’s Day
- 2 April 2026Maundy Thursday
- 3 April 2026Good Friday
- 5 April 2026Easter Sunday
- 6 April 2026Easter Monday
- 14 May 2026Ascension Day
- 24 May 2026Whit Sunday
- 25 May 2026Whit Monday
- 25 December 2026Christmas Day
- 26 December 2026Boxing Day