Section 8

Chapter 2 – Scope

The consolidated text in force from 6 February 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

(1) Where works, the provision of services or the purchase of similar supplies are awarded in the form of separate lots, Part II or III applies to the award of each lot, provided that the aggregate value of all the lots is equal to or greater than the applicable threshold.

(2) Notwithstanding subsection (1), a contracting authority may award a lot without applying the rules of Part II or III where the following conditions are met:

(i) The estimated value of the lot concerned is less than DKK 596,408 excluding VAT for supplies and services, or less than DKK 7,455,100 excluding VAT for works, cf. however section 9.

(ii) The aggregate value of the lots awarded without applying the rules of Part II or III does not exceed 20 per cent of the aggregate value of all the lots into which the envisaged works, the envisaged purchase of similar supplies or the envisaged provision of services has been divided.

Cross-references

This section refers to

Referred to by

Decisions of the Complaints Board

Decisions in which the Complaints Board for Public Procurement applied section 8. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.

  • Case 22/14585Upheld

    Tunstall A/S v Frederikssund Kommune

    The complaint concerned Frederikssund Kommune's award, without prior procurement, of a contract for an emergency call system on the basis of an unsolicited offer just below the threshold, after the municipality had split an originally combined purchase. The Complaints Board held that the value was to be estimated when the municipality launched the procedure (section 29), that it was above the threshold, and that the municipality had not shown that the split was objectively justified under section 30(2), and annulled the award decision.

All decisions by section

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.