Consolidated Act No. 448 of 8 May 2025
Section 14
Chapter 5 – Remedies and penalties
(1) Upon a claim by the complainant, the Complaints Board for Public Procurement may order a contracting authority to pay the complainant damages for the loss which the complainant has suffered as a result of an infringement of the rules referred to in section 1(2).
(2) Where a complainant claims damages for the costs of preparing a tender or of participating in a procurement procedure which is covered by the Utilities Directive, the complainant need only prove that the contracting authority has infringed the EU procurement rules and that the complainant would have had a real chance of being awarded the contract if the rules had been complied with.