FAQ

Questions and answers on complaints to the Complaints Board for Public Procurement

Answers to the most common questions about challenging a procurement: who can complain, the time limits, standstill, suspensive effect and what the Complaints Board for Public Procurement can do.

Updated 23 November 20268 questions

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 23 November 2026

Short answers are given here. For the full explanation, read the guide to complaints and remedies.

Who can complain to the Complaints Board for Public Procurement?

Anyone with a legal interest in the matter can complain. So can the Danish Competition and Consumer Authority and the organisations and authorities the Minister has given a right to complain (section 6(1) of the Complaints Board Act). Complaints about the award of contracts under Part V of the Public Procurement Act (udbudsloven) cannot be brought before the Board (section 195(2) of the Public Procurement Act).

Legal basissection 195(2) · official text

How long is the time limit for complaining?

It depends on what is challenged. A complaint about not being selected must be made within 20 calendar days from the day after the notification (section 7(1) of the Complaints Board Act). A complaint about the award of a contract where the authority has published a notice of the concluded contract must be lodged within 45 calendar days from the day after publication (section 7(2)(i) of the Complaints Board Act). Use the deadline calculator to count the days.

What is the standstill period and why does it matter?

The contracting authority may conclude the contract only after a standstill period of 10 calendar days where notification is electronic and 15 calendar days where it is by letter (section 3(1) of the Complaints Board Act). The period gives tenderers a chance to complain before the contract is concluded. The notification must state when the period ends (section 171(4) of the Public Procurement Act).

Legal basissection 171(4) · official text

Does a complaint stop the contract?

A complaint lodged during the standstill period has suspensive effect until the Board has decided whether it should have suspensive effect until the final decision (section 12(2) of the Complaints Board Act). The Board may grant suspensive effect only where special reasons so warrant.

What can the Board do if the contracting authority has broken the rules?

It may suspend the procedure, annul unlawful decisions or the tender, order the authority to bring the procedure into compliance, and impose a financial penalty (section 13(1) of the Complaints Board Act). On request it may also order the authority to pay damages for the complainant's loss (section 14(1) of the Complaints Board Act).

When can a contract be declared ineffective?

A contract may be declared ineffective if it was concluded during the standstill period or while suspensive effect applied (section 16 of the Complaints Board Act). It must be declared ineffective if it was concluded without a contract notice in breach of the rules, see section 17(1)(i) of the Complaints Board Act. The contract may be maintained if overriding reasons relating to a general interest require it (section 17(3) of the Complaints Board Act).

Does it cost anything to complain?

The Act authorises the Minister to lay down rules on a fee for lodging a complaint (section 11(3) of the Complaints Board Act). The amount of the fee does not appear in the text of the Act but in the rules issued under that authorisation.

Can I go straight to the courts?

A complaint made during the standstill period cannot be brought before the courts until the Board has decided (section 5(1) of the Complaints Board Act). The Board's decision may be brought before the courts no later than 8 weeks after it was communicated to the parties (section 8(1) of the Complaints Board Act). The time limits for complaints also apply to court actions (section 7(6) of the Complaints Board Act).