Consolidated Act No. 116 of 3 February 2025 · Part III · Procurement of social and other specific services above the threshold
Section 188
Chapter 16 – Procedures and publication of notices and announcements
(1) A contracting authority shall award contracts in accordance with the procedure which it has laid down, cf. section 186.
(2) Notification of candidates and tenderers shall be made in accordance with section 171.
(3) A contracting authority may conclude a contract at the earliest when the standstill period has expired, cf. section 3(1) or (2) of the Act on the Complaints Board for Public Procurement.
Cross-references
This section refers to
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 188. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 26/05902Not upheld
Apovac F.M.B.A. v Region Midtjylland, Region Nordjylland, Region Syddanmark, Region Sjælland og Region Hovedstaden
The complaint concerned the regions' evaluation of Apovac's tender in a procurement of social and other specific services under Part III of the Public Procurement Act concerning vaccinations by private providers. The Complaints Board found that under sections 186 and 188 the regions had a very wide discretion, that the evaluation followed the method set out in the tender conditions, and that the finding that it was unclear whether replacement staff had been trained did not rest on an incorrect factual basis, so section 2 was not breached.
Provisions applied: section 2, section 186, section 188Read the decision (Danish)Case 24/06844Not upheld
SurgiTeam P/S v Region Sjælland
SurgiTeam complained about Region Sjælland's evaluation of tenders for a framework agreement for locum doctors, procured under the regime for social and other specific services (Part III of the Act), and that the evaluation model was not transparent. The Complaints Board found that the region had not exceeded its broad discretion in the qualitative evaluation of security of supply, and that despite some unclear wording the evaluation model was a relative model, so there was no breach of sections 186 and 188(1) or of the principles in section 2.
Provisions applied: section 2, section 186, section 188(1)Read the decision (Danish)Case 23/13174Partly upheld
Silkeborg Jordemoderhus ApS v Region Syddanmark
The complaint concerned Region Syddanmark's cancellation of a procurement under Part III of the Act for a private maternity clinic, in which the complainant was the only tenderer, and the conduct of the negotiations. The Complaints Board found that the cancellation was objectively justified, as only one tender had been received and it did not meet the region's expectations, but that the region breached the principle of transparency in section 2, which under section 186 also applies to social and other specific services, by negotiating on final tenders in several rounds contrary to the tender conditions.
Provisions applied: section 2, section 186, section 188(2)Read the decision (Danish)Case 23/07970Upheld
Powercare A/S v Region Hovedstaden
Powercare complained that, in a procurement under Part III (social and other specific services) of framework agreements for temporary healthcare staff, Region Hovedstaden had changed the minimum requirement on references for technical and professional ability by a corrigendum notice. The Complaints Board found that section 2 applies through section 186, that changing a minimum requirement of suitability is as a starting point a modification of an essential element, and that the region had not proved that the change could not have affected participation, so the award decision was annulled.
Provisions applied: section 2, section 7, section 186, section 188(1)Read the decision (Danish)Case 21/07807Upheld
Attendo A/S v Greve Kommune
Attendo challenged Greve Kommune's Part III procurement for the operation of a care home, in which the procurement documents gave information on the incumbent's staff to be taken over under the Danish transfer-of-undertakings legislation. The Complaints Board found that the information was incorrect and misleading because hourly-paid staff were not included, that the municipality's later clarification changed a fundamental element contrary to section 2, and that the award decision did not meet the requirement to give reasons in section 188(2), cf. section 171(4); the award decision was annulled.
Provisions applied: section 2, section 171(4)(ii), section 188(2)Read the decision (Danish)
On this site
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.