Abnormally low tenders under the Public Procurement Act: explanation, rejection and State aid

What a contracting authority must do when a tender appears abnormally low, when the tender may or must be rejected, and how the rules fit with the award of the contract.

Updated 23 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 23 November 2026

Legal basissection 169(1) · section 169(2) · section 169(3) · section 169(4) · section 169(5) · section 159(1) · section 159(7) · section 164(1) · section 164(2) · official text

A tender with a very low price may be a good tender, but it may also be a sign that the tenderer cannot deliver as promised, or that the price was achieved by disregarding labour, environmental or social rules. The Public Procurement Act (udbudsloven) sets no percentage threshold for when a tender is abnormally low. Instead it lays down how the contracting authority must proceed when a tender appears abnormally low.

How the rule fits with the award

The rule on abnormally low tenders forms part of the award stage. The authority must award the contract in accordance with the rules on award criteria and, where relevant, on life-cycle costing and abnormally low tenders (section 159(1) of the Public Procurement Act). The award criteria must be transparent and accompanied by specifications that allow the information provided by tenderers to be effectively verified (section 164(1) of the Public Procurement Act). In cases of doubt the authority must carry out an effective check of the information and evidence in the tender (section 164(2) of the Public Procurement Act). See award criteria and award and standstill.

Step 1: ask for an explanation

Where a tender appears abnormally low, the authority must request the tenderer to explain, within an appropriate time limit, the prices and costs included in the tender (section 169(1) of the Public Procurement Act). This is a duty, not an option. The authority therefore cannot reject a tender merely because the price seems low without first giving the tenderer the opportunity to explain it.

In practice the authority should:

  • state which parts of the tender give rise to doubt and why (for example deviations from the other tenders or from its own estimate)
  • set a time limit proportionate to the complexity of the case
  • ask for supporting documents, such as calculations, hourly rates and supplier agreements
  • document its assessment of the reply.

Step 2: assess the explanation

The authority may reject a tender as abnormally low only where the price or cost level offered cannot be justified on the basis of the tenderer's explanation (section 169(2) of the Public Procurement Act). The explanation may relate, among other things, to:

The list shows which explanations are legitimate. If the explanation is credible and documented, the tender should in principle be assessed together with the others.

Duty to reject: environmental, social and labour law

The authority must reject a tender where it is abnormally low because the tenderer or its subcontractor has violated applicable obligations in environmental, social and labour law (section 169(3) of the Public Procurement Act). This may concern, for example, pay and working conditions that do not follow legislation or collective agreements. The authority has no discretion here: the link between the low price and the violation triggers rejection.

The Act also gives a general possibility of not awarding the contract to the tenderer submitting the most economically advantageous tender if, after hearing the tenderer, the authority can prove that the tender does not comply with these obligations (section 159(7) of the Public Procurement Act).

State aid

A tender may be rejected on the ground that the tenderer has received State aid only if the tenderer has not shown, within an appropriate time limit, that the aid is compatible with the internal market (section 169(4) of the Public Procurement Act). If the authority rejects on this basis, it must notify the Danish Competition and Consumer Authority (KFST), which informs the European Commission (section 169(5) of the Public Procurement Act).

Overview

SituationAuthority's optionsProvision
Tender appears abnormally lowMust request an explanationsection 169(1) of the Public Procurement Act
Explanation cannot justify the price levelMay reject the tendersection 169(2) of the Public Procurement Act
Low price results from breach of environmental, social or labour lawMust reject the tendersection 169(3) of the Public Procurement Act
Low price results from State aidMay reject if compatibility is not shown; must notify KFSTsection 169(4) of the Public Procurement Act, section 169(5) of the Public Procurement Act

Practical advice

  • Contracting authorities: do not reject a tender on price alone. Follow the procedure, keep the correspondence and state the reasons in the notification to tenderers. A mistake here may give rise to a complaint.
  • Tenderers: have your calculation ready so that you can explain the price, and note that a subcontractor's breach of the rules can also lead to rejection.
  • The question may also arise where several tenders lie well below the authority's estimate. That is not in itself a ground for rejection.