Must the sub-criteria be weighted, and where must this be stated?
Yes, under the best price-quality ratio the authority must state in the procurement documents how the sub-criteria are weighted (section 165(1) of the Public Procurement Act). The weighting may be expressed as a range (section 165(2) of the Public Procurement Act), and where weighting is objectively impossible, the criteria must be listed in order of priority (section 165(3) of the Public Procurement Act).
Legal basissection 165(1) · section 165(2) · section 165(3) · official text
What must the notification of an award contain?
It must state when the standstill period expires and be accompanied by reasons. Rejected tenderers must be given the grounds for rejection, and tenderers with an acceptable tender must be given the characteristics and advantages of the winning tender and the winner's name (section 171(4) of the Public Procurement Act).
Legal basissection 171(4) · official text
How long is the standstill period?
At least 10 calendar days from the day after dispatch if the notification is sent electronically, and 15 calendar days if it is sent by letter (section 3(1) of the Complaints Board Act). The authority may fix a longer period (section 3(2) of the Complaints Board Act). See the guide on award and standstill.
When does the standstill period not apply?
For example in procedures without a prior contract notice, for awards under a framework agreement or within a dynamic purchasing system, and where the only affected tenderer is the one awarded the contract (section 3(3) of the Complaints Board Act).
When must a contract award notice be sent?
No later than 30 days after the contract or framework agreement is concluded (section 129(1) of the Public Procurement Act). For contracts under a dynamic purchasing system, notices must be sent no later than 30 days after the end of each quarter (section 129(4) of the Public Procurement Act).
Legal basissection 129(1) · section 129(4) · official text
Related pages
Previous topic
Frequently asked questions on exclusion, suitability and selection
Next topic
Questions and answers on complaints to the Complaints Board for Public Procurement
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.