Award decision, notification and the standstill period

What the contracting authority must notify and give reasons for, how long the standstill period is, when the contract may be concluded at the earliest, and what applies to cancellation and contract award notices.

Updated 23 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 23 November 2026

Legal basissection 129(1) · section 129(4) · section 170(1) · section 170(2) · section 171(1) · section 171(3) · section 171(4) · section 171(5) · section 171(7) · section 172 · section 173 · section 174(1) · section 174(4) · section 174(5) · official text

Once the evaluation is complete, the contracting authority must notify the tenderers of its decision and wait before concluding the contract. The standstill period gives tenderers that missed out time to have the decision reviewed. This guide covers what the notification must contain, how long the period is, when it does not apply, and what the authority must publish afterwards.

Notification of decisions

The authority must, as soon as possible and simultaneously, notify all affected candidates and tenderers in writing of the decisions it has taken. That includes decisions on selection, on limiting the number of tenders and solutions, on the award of a contract, on admission to a dynamic purchasing system and on cancelling the procurement procedure (section 171(1) of the Public Procurement Act).

The notification of the award must state when the standstill period expires (section 171(4) of the Public Procurement Act). It must also be accompanied by reasons:

  • To tenderers whose tender was unacceptable, the authority must give the grounds on which the tender was rejected (section 171(4)(i) of the Public Procurement Act).
  • To tenderers that submitted an acceptable tender, the authority must give the characteristics and advantages of the winning tender relative to the rejected one and the name of the winning tenderer or the parties to the framework agreement. In innovation partnerships, negotiated procedures and competitive dialogue, the authority must also account for the course of the negotiations or dialogue (section 171(4)(ii) of the Public Procurement Act).

For an award under a dynamic purchasing system, reasons are given on request, and the tenderer must have them no later than 15 days after the authority received the request (section 171(5) of the Public Procurement Act).

Where a tenderer is passed over when the number of tenders is limited, the notification must give reasons and the names of those that go on (section 171(3) of the Public Procurement Act). In special cases the authority may withhold certain information if disclosure would be contrary to public interests, harm the legitimate commercial interests of particular operators, or harm effective competition (section 172 of the Public Procurement Act).

In practice, reasons that merely repeat the scores are rarely enough. They should allow the unsuccessful tenderer to judge whether the decision is right and therefore whether a complaint is worthwhile.

Length of the standstill period

The standstill period is regulated in the Act on the Complaints Board for Public Procurement. The authority may conclude the contract only after a standstill period of (section 3(1) of the Complaints Board Act):

Notification sentPeriodCounted from
Electronically10 calendar days (section 3(1)(i) of the Complaints Board Act)The day after it is sent
By letter15 calendar days (section 3(1)(ii) of the Complaints Board Act)The day after it is sent

The authority may fix a longer period (section 3(2) of the Complaints Board Act). The Public Procurement Act repeats that the contract may be concluded only once any standstill period has expired (section 173 of the Public Procurement Act).

Standstill does not apply where (section 3(3) of the Complaints Board Act):

What a complaint means in the period is covered in the guide on remedies. It is enough here to know that a complaint lodged during the standstill period has suspensive effect until the Complaints Board for Public Procurement has decided whether it should keep that effect (section 12(2) of the Complaints Board Act). A contract concluded during the standstill period may in some cases be declared ineffective (section 17(1)(ii) of the Complaints Board Act). The period runs from the day after the notification is sent, so plan the timetable from the day of dispatch. Use the deadline calculator to count.

Revoking an award decision

If the authority discovers an error in the evaluation, it may revoke the decision and resume the evaluation, provided the contract has not yet been concluded, the tender validity period has not expired, and all tenderers are notified (section 170(1) of the Public Procurement Act). It must then take a new decision on a fresh assessment of the same tenders, following the procedure described in the procurement documents (section 170(2) of the Public Procurement Act).

Cancellation

If the authority decides to cancel the procurement procedure, all affected candidates and tenderers must be notified (section 171(1)(v) of the Public Procurement Act), and the notification must give the reasons for the cancellation (section 171(7) of the Public Procurement Act). The authority must also state in its report why it decided not to award a contract or framework agreement (section 174(1)(viii) of the Public Procurement Act). The provisions read do not list the grounds on which a procedure may be cancelled, so the reasons should be objective and capable of being documented, in line with the duty to document all decisions (section 174(4) of the Public Procurement Act).

Contract award notice

No later than 30 days after a contract or framework agreement is concluded, the authority must send a contract award notice to the EU Publications Office (section 129(1) of the Public Procurement Act). It must contain the information in Annex V, part D, to the Public Procurement Directive (section 129(2) of the Public Procurement Act). Contracts based on a framework agreement may be notified (section 129(3) of the Public Procurement Act), and for dynamic purchasing systems notices must be sent no later than 30 days after the end of each quarter (section 129(4) of the Public Procurement Act). In special cases publication may be omitted if it would impede law enforcement or harm public interests, legitimate commercial interests or competition (section 129(5) of the Public Procurement Act).

Report and records

After a procurement ends, the authority must prepare a written report covering, among other things, the suitability assessment, the successful tenderer and the reasons for the choice (section 174(1) of the Public Procurement Act). If the award notice contains the information, the report may refer to it (section 174(3) of the Public Procurement Act). The authority must document the conduct of the procurement and keep the records for the whole term of the contract, and at least 3 years from the award (section 174(4) of the Public Procurement Act, section 174(5) of the Public Procurement Act).

See also the guide on award criteria.