Suitability and selection under the Public Procurement Act: minimum requirements, reliance on others and limiting candidates

How a contracting authority sets minimum requirements of suitability, how tenderers may rely on other entities and take part in groups, and how the number of candidates may be limited.

Updated 23 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 23 November 2026

Legal basissection 139 · section 140 · section 141 · section 142 · section 143 · section 144 · section 145 · section 146 · section 147 · section 154 · section 155 · official text

Suitability is about whether a company is able to perform the particular contract being tendered. Selection is about which suitable candidates the contracting authority will invite when there are more than it needs. The two must be kept apart: suitability is a yes-or-no test against minimum requirements, while selection ranks candidates that all meet them. Before either, the authority must have assessed whether the company is excluded under the Public Procurement Act (udbudsloven).

Three kinds of suitability requirement

A contracting authority may set suitability requirements relating to (section 140(1) of the Public Procurement Act):

The requirements must be set as minimum requirements in the contract notice, and the authority may apply only those that are relevant to ensuring that the company can pursue the activity and perform this contract (section 140(2) of the Public Procurement Act). This expresses the principle of proportionality: a requirement unconnected with the subject matter and scale of the contract is unlawful.

Professional activity

The authority may require enrolment on a relevant professional or trade register in the country of establishment (section 141(1) of the Public Procurement Act). Where the service requires a particular authorisation or membership of an organisation, it may require proof of it (section 141(2) of the Public Procurement Act).

Economic and financial standing

If the authority sets minimum requirements here, the contract notice must state how they are to be demonstrated (section 142(1) of the Public Procurement Act). A turnover requirement may not exceed twice the estimated value of the contract per year, except in duly justified cases of special risk, and then the requirement must be justified in the procurement documents (section 142(2) of the Public Procurement Act). Where a contract is divided into lots, the limit applies to each lot, but the authority may set a combined minimum turnover for a group of lots that may be awarded to the same tenderer and are to be performed at the same time (section 142(3) of the Public Procurement Act). For framework agreements with reopening of competition and for dynamic purchasing systems, the requirement is based on the expected maximum size of the contracts to be performed at the same time (section 142(4) of the Public Procurement Act, section 142(5) of the Public Procurement Act).

Technical and professional ability

Here too the contract notice must state how the requirements are to be demonstrated (section 143 of the Public Procurement Act). The Act lists forms of evidence, for example lists of works carried out in the past 5 years and of supplies or services in the past 3 years (section 155(i) of the Public Procurement Act, section 155(ii) of the Public Procurement Act). See the ESPD and evidence.

Reliance on other entities

A candidate or tenderer may rely on the economic and financial standing or the technical and professional ability of other entities, irrespective of the legal nature of the links between them (section 144(1) of the Public Procurement Act). This may be a parent company or a subcontractor, for example. The rules are:

Groups and consortia

Groups of economic operators, including temporary associations, may participate, and the authority may not require a specific legal form (section 139(2) of the Public Procurement Act). The authority may clarify in the procurement documents how a group is to meet the minimum requirements, where this is objectively justified and proportionate (section 139(3) of the Public Procurement Act). After the award it may require a specific legal form if necessary for satisfactory performance (section 139(5) of the Public Procurement Act). A group may also rely on other entities (section 144(7) of the Public Procurement Act), and for works, services and installation operations the authority may require critical tasks to be performed by the winning tenderer itself or a specific member of the group (section 144(8) of the Public Procurement Act).

Changes during the procedure

In certain cases the authority may accept that a supporting entity or a group member is replaced, or that the company is restructured, but not where the entity or member has been of decisive importance for the assessment of suitability, selection or evaluation (section 147(1) of the Public Procurement Act). A group cannot be extended after the time limit has expired (section 147(4) of the Public Procurement Act). After any change the authority must verify that there are no grounds for exclusion and that suitability is still met (section 147(2) of the Public Procurement Act, section 147(3) of the Public Procurement Act).

Selection among candidates

In restricted procedures, competitive procedures with negotiation, competitive dialogues and innovation partnerships, the authority may limit the number of candidates it invites (section 145(1) of the Public Procurement Act). Where more suitable candidates apply than there are places, selection must follow objective and non-discriminatory criteria. If turnover is used as a criterion, no weight may be given to the part of turnover exceeding twice the estimated contract value (section 145(2) of the Public Procurement Act).

The contract notice must state the number of candidates (possibly as a range), the information on which selection is based and the criteria applied (section 145(3) of the Public Procurement Act). The number must ensure genuine competition and is at least five in restricted procedures and at least three in the other procedures (section 145(4) of the Public Procurement Act). See procedures.

Later in the procedure the authority may reduce the number of tenders or solutions. This must be done on the basis of the award criteria laid down, and the number in the final stage must ensure genuine competition (section 146(1) of the Public Procurement Act, section 146(2) of the Public Procurement Act).

Practical advice

  • Contracting authorities: set only the requirements the contract needs, and justify a high turnover requirement.
  • Tenderers: have legally binding declarations of support ready, and agree with consortium partners who covers which requirement.

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo