The European Single Procurement Document (ESPD) and evidence under the Public Procurement Act

When the contracting authority must require the ESPD, how it may be re-used, when evidence must be submitted before the award, and which forms of evidence the authority may require.

Updated 23 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 23 November 2026

Legal basissection 148 · section 150 · section 151 · section 152 · section 153 · section 154 · section 155 · section 157 · section 158 · section 159(2) · official text

The European Single Procurement Document, or ESPD, is a self-declaration by which a company provides preliminary evidence that it is not excluded and meets the suitability requirements. The full evidence comes only later, and only from the company that is to be awarded the contract. This spares tenderers and contracting authorities from collecting and reviewing documents from every participant. The rules are in the chapter of the Public Procurement Act (udbudsloven) on evidence concerning exclusion, minimum requirements of suitability and selection.

When must the ESPD be required?

The contracting authority must require candidates and tenderers to use the ESPD as preliminary evidence that (section 148(1) of the Public Procurement Act):

If the company relies on other entities, the ESPD must also contain the information on them (section 148(2)(i) of the Public Procurement Act). The company must also indicate which public authority or third party is responsible for the evidence and confirm that it can be submitted without undue delay on request (section 148(2)(ii) of the Public Procurement Act), and state whether the authority can obtain the information from a national database (section 148(2)(iii) of the Public Procurement Act). See suitability and selection and grounds for exclusion.

The Minister for Industry, Business and Financial Affairs may lay down rules on standard forms, including for the ESPD (section 149 of the Public Procurement Act).

Re-use of the ESPD

A candidate or tenderer may re-use an ESPD used in an earlier procedure if it confirms that the information is still correct (section 150 of the Public Procurement Act). Reviewing the document is the company's responsibility: information that no longer fits, for example on debt or the composition of management, must be corrected. False information may lead to exclusion (section 136(iii) of the Public Procurement Act).

Evidence before the award

Before the authority decides on the award, it must require the tenderer to which it intends to award the contract to submit evidence of the information in the ESPD, and it must set an appropriate time limit (section 151(1) of the Public Procurement Act). The authority may also require evidence at any time if necessary for the proper conduct of the procedure (section 151(2) of the Public Procurement Act). It may ask the company to supplement or clarify the evidence (section 151(4) of the Public Procurement Act).

Evidence need not be submitted in two situations:

The requirement also does not apply to contracts based on framework agreements that are awarded without reopening competition (section 151(3) of the Public Procurement Act). See framework agreements.

The authority may award the contract only once it has verified, on the basis of the ESPD, the evidence and e-Certis, that the tenderer is not excluded, meets the suitability requirements and, where relevant, has been selected (section 159(2) of the Public Procurement Act). In an open procedure it may choose to evaluate the tenders before carrying out this verification (section 159(4) of the Public Procurement Act). In cases of doubt it must carry out an effective check (section 159(3) of the Public Procurement Act). See award and standstill.

What evidence may the authority require?

The authority may require only the forms of evidence named in the Act, plus evidence of professional activity under section 141 of the Public Procurement Act (section 152(2) of the Public Procurement Act). It must, as far as possible, require the forms listed in e-Certis (section 152(3) of the Public Procurement Act).

SubjectEvidenceProvision
Criminal offences, debt and insolvencyExtract from a register or equivalent document from a judicial or administrative authority, and a certificate from the competent authoritysection 153(1) of the Public Procurement Act
Where the country does not issue themDeclaration on oath or solemn declaration before an authority, notary or professional bodysection 153(2) of the Public Procurement Act
Economic and financial standingFor example a bank statement, professional indemnity insurance, annual accounts or a statement of turnover for up to 3 yearssection 154(1) of the Public Procurement Act
Technical and professional abilityFor example reference lists (5 years for works, 3 years for supplies and services), information on technicians, equipment, qualifications and subcontractorssection 155 of the Public Procurement Act
Quality assuranceCertificates from independent bodies; equivalent certificates from other Member States must be acceptedsection 157 of the Public Procurement Act
Environmental managementCertificates from independent bodies, for example EMASsection 158 of the Public Procurement Act

If a company cannot, for a valid reason, submit the documents required, it may demonstrate its economic standing by any other document the authority considers appropriate (section 154(2) of the Public Procurement Act). If a company cannot obtain a required quality assurance or environmental certificate within the time limit for reasons not attributable to it, the authority must accept other appropriate evidence (section 157(3)(i) of the Public Procurement Act, section 158(3)(i) of the Public Procurement Act).

A company on an official list of approved economic operators may instead submit a certificate of registration (section 152(4) of the Public Procurement Act).

Practical advice

  • Contracting authorities: state in the procurement documents which forms of evidence you will require, and set a reasonable time limit. Use e-Certis and national databases so that companies need not submit what you can obtain yourselves.
  • Tenderers: complete the ESPD carefully and review a re-used ESPD point by point. Make sure the evidence can be obtained quickly, including from any supporting entities, so that the time limit can be met.

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo