The consolidated text in force from 6 February 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

A contracting authority may require the candidate or tenderer to provide evidence of its technical and professional ability. This shall be done in one or more of the following ways:

(i) A list of the works carried out over the past five years, accompanied by certificates of satisfactory execution and outcome for the most important works. Where necessary to ensure an adequate level of competition, the contracting authority may indicate that evidence of relevant works carried out more than five years before will also be taken into account.

(ii) A list of the principal deliveries of supplies or services effected in the past three years, with the amounts, dates and public or private recipients. Where necessary to ensure an adequate level of competition, the contracting authority may indicate that evidence of relevant deliveries of supplies or services delivered or effected more than three years before will also be taken into account.

(iii) Information about the technicians or technical bodies involved, especially those responsible for quality control, whether or not they belong directly or indirectly to the candidate's or tenderer's undertaking, and, in the case of public works contracts, information about the technicians or technical bodies which the contractor can call upon to carry out the work.

(iv) A description of the technical facilities and the measures taken by the candidate or tenderer to ensure quality, and of the undertaking's study and research facilities.

(v) An indication of the supply chain management and tracking systems that the candidate or tenderer will be able to apply when performing the contract.

(vi) A check carried out by the contracting authority or on its behalf by a competent official body of the country in which the supplier or service provider is established, subject to that body's consent, on the production capacities of the supplier or the technical and professional ability of the service provider and, where necessary, on the undertaking's study and research facilities and the quality control measures it will operate. This applies only where the supplies or services to be provided are complex or, exceptionally, are required for a special purpose.

(vii) An indication of the educational and professional qualifications of the service provider or contractor or of the undertaking's managerial staff, provided that they are not evaluated as an award criterion.

(viii) An indication of the environmental management measures that the candidate or tenderer will be able to apply when performing the contract.

(ix) A statement of the service provider's or contractor's average annual manpower and the number of managerial staff for the last three years.

(x) A statement of the tools, plant or technical equipment available to the service provider or contractor for performing the contract.

(xi) An indication of the proportion of the contract which the candidate or tenderer intends possibly to subcontract.

(xii) As regards the supplies to be delivered:

(a) Samples, descriptions or photographs, the authenticity of which must be certifiable at the request of the contracting authority.

(b) Certificates drawn up by official quality control institutes or agencies of recognised competence attesting the conformity of supplies clearly identified by references to technical specifications or standards.

Decisions of the Complaints Board

Decisions in which the Complaints Board for Public Procurement applied section 155. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.

  • Case 24/09713Upheld

    Vognmand Andreas R. Søborg A/S v Odsherred Kommune

    The complaint concerned Odsherred Municipality's rejection of Søborg A/S's tender for the transport of waste from recycling centres for failing a reference requirement on technical ability based on section 155. The Complaints Board found that the requirement's alternative for new operators was unclear and could be read as covering any operator without previous experience in waste transport, and that by rejecting the tender without assessing whether Søborg A/S had otherwise shown relevant experience, the municipality breached section 2.

  • Case 22/14568Partly upheld

    Scania Danmark A/S v I/S REFA

    Scania challenged REFA's award of a contract for the supply and servicing of refuse collection vehicles to Hessel. The Complaints Board found that REFA had not verified before the award that Hessel met the minimum requirement of suitability of four references, contrary to section 159(2), and that Hessel's tender contained a reservation against the minimum requirement for LED lighting, so it should not have been considered under the principles in section 2; the award decision was annulled, while a claim about the number of vehicles stated in the tender failed.

All decisions by section

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.