Consolidated Act No. 448 of 8 May 2025
Section 18
Chapter 5 – Remedies and penalties
(1) A contract is declared ineffective in respect of future obligations under the contract. Where a contract is declared ineffective, it must be stated from what time the contract is to be regarded as ineffective, or which parts of the contract are to be regarded as ineffective.
(2) An alternative penalty is imposed under sections 19 or 20 where
(i) a contract which is covered by section 16 is not declared ineffective,
(ii) a contract which is covered by section 17(1) and which is not exempted under section 4 or section 17(2) is not declared ineffective, cf. section 17(3), or
(iii) part of a contract is declared ineffective, cf. subsection (1).
(3) Where the contracting authority is not covered by section 19(1), the Complaints Board for Public Procurement reports the matter to the police when the contracting authority is to be subject to an alternative penalty in the form of a fine pursuant to subsection (2).
Cross-references
This section refers to
Referred to by
On this site
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.