Consolidated Act No. 448 of 8 May 2025
Section 17
Chapter 5 – Remedies and penalties
(1) A contract which is covered by Part II or III of the Public Procurement Act or by the Utilities Directive must be declared ineffective if
(i) a contracting authority, in breach of the Public Procurement Act or the EU procurement rules, has entered into a contract without prior publication of a contract notice in the Official Journal of the European Union, cf. however section 4,
(ii) the contract was entered into during the standstill period, cf. section 3(1) and (2), or the contract was entered into during a period in which a complaint has suspensive effect, cf. section 12, and the contracting authority has at the same time infringed the Public Procurement Act or the EU procurement rules in a way that has affected the complainant’s chances of being awarded the contract,
(iii) the contract is based on a framework agreement with reopening of competition and was entered into in breach of Part II or III of the Public Procurement Act, and the estimated contract value is equal to or exceeds the threshold laid down in those rules, cf. however subsection (2), or
(iv) the contract is based on a dynamic purchasing system and was entered into in breach of Part II or III of the Public Procurement Act or the Utilities Directive, and the estimated contract value is equal to or exceeds the threshold laid down in those rules, cf. however subsection (2).
(2) In the cases referred to in subsection (1)(iii) and (iv), a contract cannot be declared ineffective if
(i) the contracting authority has followed the procedures in sections 2 and 3 or section 171 of the Public Procurement Act, and
(ii) the contracting authority considers that the contract based on a framework agreement with reopening of competition or a dynamic purchasing system was entered into in accordance with the Public Procurement Act or the EU procurement rules.
(3) A contract which is to be declared ineffective under subsection (1) and which is not exempted under section 4 or subsection (2) may be maintained if, on the basis of an examination of all relevant aspects, it must be found that overriding reasons relating to a general interest require that the contract should continue to have effect.
(4) The Complaints Board for Public Procurement informs the Danish Competition and Consumer Authority and the European Commission of decisions taken by the Complaints Board for Public Procurement pursuant to subsection (3).
(5) Where the decision to award a central purchasing body’s framework agreement has not been annulled, cf. section 13(1)(ii), at the time of initiation of the award procedure for a contract based on the framework agreement, the contract cannot be declared ineffective on the ground that the central purchasing body has made errors, cf. however subsection (1)(ii) and (iii).
Cross-references
This section refers to
Referred to by
On this site
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.