Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold
Section 123 Joint procurement
Chapter 9 – Joint procurement
(1) Contracting authorities may agree to conduct procurement jointly.
(2) Where a procurement procedure is conducted jointly in its entirety in the name and on behalf of all the participating contracting authorities, the participating contracting authorities shall be jointly responsible for fulfilling their obligations under this Act.
(3) Where one or more contracting authorities have been selected from among the participating contracting authorities to conduct the procurement procedure and to act in their own name and on behalf of the other participating contracting authorities, the participating contracting authorities shall be jointly responsible for fulfilling their obligations under this Act.
(4) Where a procurement procedure is not conducted jointly in its entirety pursuant to subsection (2), the participating contracting authorities shall be jointly responsible only for fulfilling their obligations under this Act in respect of the parts conducted jointly. Each contracting authority shall have sole responsibility for fulfilling its obligations under this Act in respect of the parts which it conducts in its own name and on its own behalf.
(5) The contract notice shall contain information making it possible to identify all the participating contracting authorities in the joint procurement. It shall also appear from the procurement documents which parts of the procurement process each contracting authority is responsible for.
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 123. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 22/14580Partly upheld
Mediq Danmark A/S v Høje-Taastrup Kommune, Brøndby Kommune, Køge Kommune og Odsherred Kommune
The complaint concerned four municipalities' joint procurement of a framework agreement for clinical nutrition and utensils. The Complaints Board found that the municipalities breached the principles of equal treatment and transparency in section 2 because the contract notice referred to one framework agreement while the procurement documents provided for four, and annulled the award decision; the description by product categories under section 45(1), the evaluation model based on a basket of goods under section 45(2) and section 160(1), and the listing of historical consumption under section 42(1) were lawful.
Provisions applied: section 2, section 42(1), section 45(1), section 45(2), section 49, section 123(3), section 160(1), section 185(2)Read the decision (Danish)
Previous section
Section 122 — Centralised purchasing activities and central purchasing bodies
Next section
Section 124 — Procurement involving contracting authorities from different Member States of the EU
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.