Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold

Section 185 Termination of contracts

Chapter 15 – Performance of contracts

The consolidated text in force from 6 February 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

(1) The contracting authority may terminate a contract or framework agreement where

(i) the contract or framework agreement has been subject to a modification of essential elements which would have required a new procurement procedure, cf. section 178,

(ii) the contractor was, at the time of the award of the contract, covered by one of the grounds for exclusion in sections 135-137, on which basis the contractor should have been excluded from the procurement procedure,

(iii) the contractor becomes, during the term of the contract or framework agreement, covered by one of the grounds for exclusion in sections 135-137 and cannot provide evidence of its reliability pursuant to section 138, or

(iv) the contract or framework agreement should not have been awarded to the contractor because of a serious infringement of the obligations under the Treaties and the Directive that has been declared by the Court of Justice of the European Union in a procedure under Article 258 of the Treaty on the Functioning of the European Union.

(2) Where an award decision has been annulled by a final decision or judgment, the contracting authority shall terminate, with reasonable notice, a contract or framework agreement concluded on the basis of the decision, unless special circumstances militating in favour of continuing the contract apply. This provision does not apply where sections 16 or 17 on ineffectiveness in the Act on the Complaints Board for Public Procurement apply. Any decision of the contracting authority to continue the contract shall be published in the same place as the procurement documents no later than 7 calendar days after the publication of the final decision or judgment.

Decisions of the Complaints Board

Decisions in which the Complaints Board for Public Procurement applied section 185. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.

  • Case 25/06657Dismissed

    City Container Danmark A/S v Gribskov Genbrug & Ressourcer A/S

    City Container challenged Gribskov Genbrug's decision to continue waste collection contracts after the Complaints Board had annulled the award decision and damages had been paid to another tenderer. The Complaints Board found that the decision had been published in the same place as the procurement documents in accordance with section 185(2), so the 20-day time limit for complaints ran from that publication, and dismissed the complaint as lodged too late.

  • Case 24/03766Not upheld

    Scania Danmark A/S v I/S REFA

    Scania complained that REFA had not terminated its contract with Ejner Hessel after the Complaints Board had annulled the award decision. The Board found that the annulment only became final when the time limit for bringing the case before the courts expired on 10 April 2024, so the 7-day time limit in section 185(2) had not yet expired when the complaint was lodged, and since REFA terminated the contract on 30 April 2024 there was no breach; the claim for an order to terminate was dismissed as no longer relevant.

  • Case 23/07577Partly upheld

    DriveClever A/S v Københavns Kommune

    DriveClever challenged the evaluation method Københavns Kommune used in a procurement of a framework agreement for vehicle maintenance based on a product range. The Complaints Board found that the municipality had not shown that the prices evaluated for one model per brand were representative of the brand's other models, so the evaluation was not based on a representative sample under section 45(2); the award decision was annulled, but the claim to order termination of the contract was dismissed because that obligation follows directly from section 185(2).

  • Case 22/14580Partly upheld

    Mediq Danmark A/S v Høje-Taastrup Kommune, Brøndby Kommune, Køge Kommune og Odsherred Kommune

    The complaint concerned four municipalities' joint procurement of a framework agreement for clinical nutrition and utensils. The Complaints Board found that the municipalities breached the principles of equal treatment and transparency in section 2 because the contract notice referred to one framework agreement while the procurement documents provided for four, and annulled the award decision; the description by product categories under section 45(1), the evaluation model based on a basket of goods under section 45(2) and section 160(1), and the listing of historical consumption under section 42(1) were lawful.

  • Case 21/10894Partly upheld

    Atea A/S v Region Sjælland

    The complaint concerned a framework agreement for an indoor mobile coverage system (DAS) for Region Sjælland's hospitals, where the drawings provided were not accurate. The Complaints Board held that the region breached section 2(1) by not neutralising the incumbent's competitive advantage as far as possible and by not publishing an extension of the time limit as a corrigendum to the contract notice, but rejected the claims on a change of fundamental elements and an insufficient extension of the time limit under section 93(4); it annulled the award decision.

  • Case 21/13160Upheld

    Peab Asfalt A/S v Øresundsbro Konsortiet I/S

    Peab complained that Øresundsbro Konsortiet had not stated the estimated quantity or value of the services to be provided in the contract notice for a framework agreement for paving works. Referring to the Court of Justice's judgment in Case C-23/20, the Complaints Board found that the requirement also applies to services and that the consortium had breached sections 56 and 128(2) and section 2; it annulled the award decision and stated that there were no special circumstances justifying continuation of the contract under section 185(2).

  • Case 19/06361Upheld

    Simonsen & Weel A/S v Region Nordjylland og Region Syddanmark

    Simonsen & Weel complained that the regions had stated neither the estimated quantity or value of the tube-feeding products to be supplied under a framework agreement in the contract notice, nor a maximum quantity or value in the procurement documents. Following the Court of Justice's answer to the Board's preliminary reference (Case C-23/20), the Complaints Board found breaches of sections 56 and 128(2) and section 2, annulled the award decision and stated that there were no special circumstances justifying continuation of the framework agreement under section 185(2).

All decisions by section