Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold
Section 61 Competitive procedure with negotiation
Chapter 7 – Procurement procedures and design contests
(1) A contracting authority may use a competitive procedure with negotiation in the following cases:
(i) For works, supplies or services fulfilling one or more of the following criteria:
(a) the needs of the contracting authority cannot be met without adaptation of readily available solutions,
(b) the contract includes design or innovative solutions,
(c) the contract cannot be awarded without prior negotiations because of specific circumstances related to its nature, its complexity or the legal and financial make-up or because of the risks attaching to them, including a need to adapt the tenders to the specific circumstances of the contract, or
(d) the technical specifications cannot be established with sufficient precision by the contracting authority with reference to a standard, a European Technical Assessment, a common technical specification or a technical reference, cf. points 2 to 5 of Annex VII to Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65).
(ii) Where, in response to an open or restricted procedure, only irregular or unacceptable tenders were submitted, cf. subsections (2) and (3).
(2) Irregular tenders under subsection (1)(ii) means in particular tenders where
(i) the tender does not comply with the requirements of the procurement documents,
(ii) the tender was received late,
(iii) there is evidence of collusion or corruption, or
(iv) the contracting authority has found the tender to be abnormally low.
(3) Unacceptable tenders under subsection (1)(ii) means in particular tenders that
(i) have been submitted by tenderers that do not meet the minimum requirements of suitability laid down, or
(ii) exceed the budget of the contracting authority as determined and documented before the procedure was launched.
(4) Where a contracting authority makes use of the possibility in subsection (1)(ii), the contracting authority is not required to publish a contract notice where the procedure includes all of the tenderers, and only those tenderers, that during the preceding open or restricted procedure submitted tenders in accordance with the formal requirements of the procurement procedure and that meet the requirements of the second sentence of section 159(2), paragraphs (i)-(iii).
Cross-references
This section refers to
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 61. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 25/05371Not upheld
Ketner-Utsch A/S v Skatteforvaltningen v/Motorstyrelsen
Ketner challenged Motorstyrelsen's use of the competitive procedure with negotiation for a 10-year contract for the production and supply of number plates, its requirement for aluminium plates made from aluminium strip, and the classification of the agreement as a public contract rather than a framework agreement. The Complaints Board found that the conditions of section 61(1)(i)(c) were met, that the requirement was covered by section 42(1)(ii) but justified by the subject-matter of the contract and could therefore be set without the words «or equivalent», and that the agreement was a public contract, not a framework agreement.
Provisions applied: section 24(xxiv), section 24(xxx), section 42(1)(ii), section 42(2), section 61(1)(i)(c)Read the decision (Danish)Case 23/12704Not upheld
Würth Danmark A/S v Forsvarsministeriets Materiel- og Indkøbsstyrelse
Würth complained that FMI, after an open procedure for a framework agreement for hand tools and similar products, had switched to a competitive procedure with negotiation, and about the evaluation of the winning tender from Lemvigh-Müller and the reasons given for the award decision. The Complaints Board found that all tenders in the open procedure were irregular, so the switch was lawful under section 61(1)(ii), cf. subsection (2)(i), that the errors FMI should have priced into the winning tender would only have caused an insignificant drop in points, and that the notification met section 171, since under section 172 FMI did not have to disclose points per product line.
Case 24/01827Partly upheld
Bruker Nordic AB v Syddansk Universitet
Bruker Nordic complained that, after an open procedure, SDU moved to a competitive procedure with negotiation without a new contract notice and awarded the contract to MR Solutions, which had been allowed after the time limit to rely on the financial capacity of a group company. The Complaints Board found that SDU had thereby allowed a new tender, contrary to section 2 and section 159(5), and that, as MR Solutions did not meet the suitability requirements, SDU was not entitled to include it in the procedure under section 61(4); the award decision was annulled, but the contract was not declared ineffective because a contract notice had been published for the preceding open procedure.
Provisions applied: section 2, section 61(1)(ii), section 61(4), section 159(2)(ii), section 159(5)Read the decision (Danish)Case 23/12074Partly upheld
Nuuday A/S v Staten og Kommunernes Indkøbsservice A/S
Nuuday complained that, after a restricted procedure for a framework agreement on communication products, SKI had switched to a competitive procedure with negotiation although, in Nuuday's view, its first tenders were compliant. The Complaints Board found that the tender conditions' error margin of up to two per cent covered Nuuday's errors, so SKI had not shown that the conditions in section 61(1)(ii) were met and the switch breached section 2, and it annulled the award decisions; the claim for ineffectiveness was rejected because, in a change of its practice, the Board held that a contract awarded after a procedure under section 61(1)(ii), cf. subsection (4), is not a direct award.
Provisions applied: section 2, section 61(1)(ii), section 61(4)Read the decision (Danish)Case 21/02695, 21/02964 og 21/02965Partly upheld
Albertslund Tømrer og Snedker A/S, VVS & Varmeteknik A/S og HRH EL A/S v Albertslund Kommune
Three craft firms that had not been selected challenged Albertslund Kommune's use of the competitive procedure with negotiation for framework agreements for craft services. By a majority, the Complaints Board found that the municipality had not shown that the conditions of section 61(1)(i)(a) and (d) were met, since the services were ordinary standard services, and annulled the award decisions for the lots the complainants had applied for; the claims concerning minimum requirements, ineffectiveness and a financial penalty were not upheld.
Provisions applied: section 55, section 61(1)(i)(a), section 61(1)(i)(d), section 174(1)(v)Read the decision (Danish)
On this site
Previous section
Section 60 — Restricted procedure
Next section
Section 62 — Competitive procedure with negotiation