Consolidated Act No. 116 of 3 February 2025 · Part I · General provisions
Section 24
Chapter 3 – Definitions
In this Act, the following definitions apply:
(i) Ancillary purchasing activities: Activities consisting in the provision of support to purchasing activities, in particular in the following forms:
(a) technical infrastructure enabling contracting authorities to award public contracts or to conclude framework agreements for works, supplies or services,
(b) advice on the conduct or design of public procurement procedures, and
(c) preparation and management of procurement procedures on behalf of and for the account of the contracting authority concerned.
(ii) Readily available solution: A solution which already exists on the market and which does not require adaptation to meet the needs of a contracting authority.
(iii) Variant: A tender which, at the request of the contracting authority, contains alternative solutions to the contracting authority's procurement needs and which deviates from what is laid down in the procurement documents.
(iv) Candidate: An economic operator that has sought an invitation or has been invited to take part in a restricted procedure, a competitive procedure with negotiation, a competitive dialogue, an innovation partnership or a negotiated procedure without prior publication.
(v) Works: The outcome of building or civil engineering works taken as a whole which is sufficient in itself to fulfil an economic or technical function.
(vi) Centralised purchasing activities: Activities conducted on a permanent basis, in one of the following forms:
(a) the acquisition of supplies or services intended for other contracting authorities, or
(b) the award of public contracts or the conclusion of framework agreements for works, supplies or services intended for other contracting authorities.
(vii) CPV code: A code appearing in the Common Procurement Vocabulary, cf. Regulation (EC) No 2195/2002 of the European Parliament and of the Council of 5 November 2002 on the Common Procurement Vocabulary (CPV) (OJ 2002 L 340, p. 1), and in any delegated acts adopted by the European Commission pursuant to Article 23(2) of the Directive in accordance with Article 87 of the Directive.
(viii) Electronic auction: A repetitive electronic process used for ranking tenders on the basis of automatic evaluation methods.
(ix) Electronic catalogue: A format for the presentation and organisation of information in a manner common to all the participating tenderers and which lends itself to electronic treatment, including tenders presented in the form of a spreadsheet.
(x) Electronic means: Electronic equipment for the processing and storage of data which is transmitted, conveyed and received by wire, by radio, by optical means or by other electromagnetic means.
(xi) The Defence and Security Directive: Directive 2009/81/EC of the European Parliament and of the Council of 13 July 2009 on the coordination of procedures for the award of certain works contracts, supply contracts and service contracts by contracting authorities or entities in the fields of defence and security, and amending Directives 2004/17/EC and 2004/18/EC (OJ 2009 L 216, p. 76).
(xii) The Utilities Directive: Directive 2014/25/EU of the European Parliament and of the Council of 26 February 2014 on procurement by entities operating in the water, energy, transport and postal services sectors and repealing Directive 2004/17/EC (OJ 2014 L 94, p. 243).
(xiii) European Single Procurement Document: A document consisting of a self-declaration drawn up on the basis of a standard form established by the European Commission, which serves as preliminary evidence in the assessment of whether a ground for exclusion exists and whether the relevant minimum requirements of suitability are met.
(xiv) Non-central government contracting authorities: Contracting authorities that are not covered by the definition of central government contracting authorities. Non-central government contracting authorities include regions, municipalities and bodies governed by public law.
(xv) Central purchasing body: A contracting authority which provides centralised purchasing activities.
(xvi) Procurement adviser: A public or private body which offers ancillary purchasing activities on the market.
(xvii) Innovation: The implementation of a new or significantly improved product, service or process, including but not limited to production, building or construction processes, a new marketing method, or a new organisational method in business practices, workplace organisation or external relations.
(xviii) Conflicts of interest: Situations where a person at a contracting authority or at a procurement adviser acting on behalf of the contracting authority, who is involved in the conduct of the procurement procedure or who may influence the outcome of that procedure, has, directly or indirectly, a financial, economic or other personal interest which might be perceived to compromise that person's impartiality and independence in the context of the procurement procedure. Conflicts of interest may also arise where an economic operator has conflicting interests which may adversely affect the performance of the contract.
(xix) The Concessions Directive: Directive 2014/23/EU of the European Parliament and of the Council of 26 February 2014 on the award of concession contracts (OJ 2014 L 94, p. 1).
(xx) Life cycle: All consecutive and/or interlinked stages, including research and development to be carried out, production, trading and its conditions, transport, use and maintenance, throughout the existence of the product or the works or the provision of the service, from raw material acquisition or generation of resources to disposal, clearance and end of service or utilisation.
(xxi) Label: Any document, certificate or attestation confirming that the works, product, service, process or procedure in question meets certain label requirements.
(xxii) Label requirements: The requirements to be met by the works, products, services, processes or procedures in question in order to obtain the label concerned.
(xxiii) Public works contracts: Public contracts having as their object one of the following:
(a) the execution, or both the design and execution, of works related to one of the activities listed in Annex II to Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65),
(b) the execution, or both the design and execution, of works, cf. paragraph (v), or
(c) the realisation, by whatever means, of works, cf. paragraph (v), corresponding to the requirements specified by the contracting authority which exercises a decisive influence on the type or design of the works.
(xxiv) Public contracts: Contracts for pecuniary interest concluded in writing between one or more economic operators and one or more contracting authorities and having as their object the execution of works, the supply of products or the provision of services.
(xxv) Public service contracts: Public contracts having as their object the provision of services other than the execution of works.
(xxvi) Public supply contracts: Public contracts having as their object the purchase, lease, rental or hire-purchase, with or without an option to buy, of products.
(xxvii) Bodies governed by public law: Bodies
(a) established for the specific purpose of meeting needs in the general interest, not having an industrial or commercial character,
(b) having legal personality, and
(c) financed, for the most part, by the State, regional or municipal authorities, or by other bodies governed by public law; or subject to management supervision by those authorities or bodies; or having an administrative, managerial or supervisory board, more than half of whose members are appointed by the State, regional or municipal authorities, or by other bodies governed by public law.
(xxviii) Contracting authority: Central government, regional and municipal authorities, bodies governed by public law and associations formed by one or more such authorities or one or more such bodies governed by public law.
(xxix) Design contest: Those procedures which enable the contracting authority to acquire, mainly in the fields of town and country planning, architecture and engineering or data processing, a plan or design selected by a jury after being put out to competition with or without the award of prizes.
(xxx) Framework agreement: An agreement between one or more contracting authorities and one or more economic operators, the purpose of which is to establish the terms governing contracts to be awarded during a given period, in particular with regard to price and, where appropriate, the quantity envisaged.
(xxxi) Parallel tender: A tender in respect of which the contracting authority has laid down in the procurement documents that several tenders may or must be submitted for the performance of the task put out to tender, using different methods of execution, materials or similar.
(xxxii) In writing: Any expression consisting of words or figures which can be read, reproduced and subsequently communicated, including information transmitted and stored by electronic means.
(xxxiii) Central government contracting authorities: Contracting authorities which form part of the central government administration.
(xxxiv) Tenderer: An economic operator that has submitted a tender.
(xxxv) The Directive: Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65).
(xxxvi) Procurement documents: Any document produced or referred to by the contracting authority to describe or determine elements of the procurement or the procedure, including
(a) the contract notice,
(b) the technical specifications,
(c) the descriptive document,
(d) the proposed conditions of contract,
(e) formats for the presentation of documents by candidates and tenderers,
(f) information on generally applicable obligations, and
(g) any additional documents.
(xxxvii) Modification of essential elements: A modification which could have allowed the admission of other candidates or tenderers than those initially selected or the acceptance of a tender other than that originally accepted, or which could have attracted additional participants in the procurement procedure, or which could have distorted competition among candidates or tenderers, had the modification been part of the initial procedure for the award of the contract.
(xxxviii) Economic operator: Any natural or legal person or public entity or group of such persons and/or entities, including any temporary association of undertakings, which offers the execution of works and/or a work, the supply of products or the provision of services on the market.
(xxxix) Evaluation model: The tool or tools used by the contracting authority to compile the tenderers' responses to the various award criteria in order to identify the most economically advantageous tender.
Cross-references
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 24. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 24/10982Partly upheld
Zeppelin Danmark A/S v Forsvarsministeriets Materiel- og Indkøbsstyrelse
Zeppelin challenged FMI's switch, after an open procedure in which no tenders were received, to a negotiated procedure without prior publication ending in a framework agreement for wheel loaders with Volvo. The Complaints Board found the switch lawful under section 80(1)(i) and the length of the negotiations not disproportionate, but held that FMI had changed fundamental elements contrary to section 80(2) by accepting a model that did not meet the minimum requirements and by changing the price structure; the framework agreement was declared ineffective and a financial penalty imposed.
Provisions applied: section 2(1), section 24(xxxvii), section 80(1)(i), section 80(2)Read the decision (Danish)Case 25/05371Not upheld
Ketner-Utsch A/S v Skatteforvaltningen v/Motorstyrelsen
Ketner challenged Motorstyrelsen's use of the competitive procedure with negotiation for a 10-year contract for the production and supply of number plates, its requirement for aluminium plates made from aluminium strip, and the classification of the agreement as a public contract rather than a framework agreement. The Complaints Board found that the conditions of section 61(1)(i)(c) were met, that the requirement was covered by section 42(1)(ii) but justified by the subject-matter of the contract and could therefore be set without the words «or equivalent», and that the agreement was a public contract, not a framework agreement.
Provisions applied: section 24(xxiv), section 24(xxx), section 42(1)(ii), section 42(2), section 61(1)(i)(c)Read the decision (Danish)Case 23/03579Upheld
Assemble A/S v Hørsholm Kommune
The complaint concerned Hørsholm Municipality's change of two minimum requirements after the negotiation meetings in a competitive procedure with negotiation for a day-care place allocation system. The Complaints Board found that the municipality had not shown that the changes, made at the winning tenderer's request, could not have affected participation or distorted competition, and that it had therefore changed basic elements contrary to section 66(5) and the principle of equal treatment in section 2.
Provisions applied: section 2, section 24(xxxvii), section 66(5)Read the decision (Danish)Case 22/14549Partly upheld
Konsortiet Abena A/S og Coloplast Danmark A/S v Esbjerg Kommune, Middelfart Kommune, Vejle Kommune, Herning Kommune, Fanø Kommune, Vejen Kommune, Varde Kommune og Billund Kommune
The consortium challenged the municipalities' procurement of a framework agreement for ostomy products. The Complaints Board found that the agreement was for pecuniary interest and thus a public contract subject to procurement under section 24(xxiv), and that the municipalities had breached section 2 by not stating a maximum quantity or value for the framework agreement and by capitalising errors in the price lists contrary to the procurement documents; the claims concerning grounds for exclusion, the quality evaluation and unclear requirements were rejected, and the award decision was annulled.
Provisions applied: section 2, section 24(xxiv), section 56, section 128(2), section 137Read the decision (Danish)Case 22/14556Upheld
Intervare A/S v Køge Kommune
Intervare complained that Køge Kommune had concluded contracts for home delivery of groceries to eligible citizens without publishing a contract notice. The Complaints Board found that these were public contracts under section 24(xxiv) and that the municipality's estimate of their value under sections 29 and 30 rested on a wrong delivery frequency and on historical prices alone, so it had not shown that the threshold in section 7 was not reached; the contracts were declared ineffective from 1 August 2023 and a financial penalty of DKK 135,000 was imposed.
Provisions applied: section 7, section 24(xxiv), section 29, section 30(1)Read the decision (Danish)Case 22/14577Partly upheld
Dustin A/S v Staten og Kommunernes Indkøbsservice A/S
Dustin challenged several aspects of SKI's procurement of a framework agreement for computers, including an extension of the time limit, modifications of the procurement documents, references to specific makes and the award to Comm2IG. The Complaints Board found that SKI breached section 2 by sending the notice extending the time limit to the EU Publications Office only after the time limit had expired and, by a majority, by awarding both lots to Comm2IG without the check described in the tender conditions although its tenders were non-compliant, and annulled the award decision, while the claims concerning modifications of the procurement documents (sections 93 and 134) and section 42 were rejected.
Provisions applied: section 2, section 24(xxxvii), section 42(2), section 93(3), section 93(4)(ii), section 134(1), section 134(2)Read the decision (Danish)Case 21/05033Partly upheld
JK Office ApS v Skive Kommune
JK Office complained about Skive Municipality's award of a framework agreement for office furniture, claiming among other things that the winning tender was non-compliant, that the minimum requirements and the evaluation model were unclear, and that the reasons for the award decision were inadequate. The Complaints Board found the winning tender compliant, the minimum requirements clear and the evaluation adequately described under section 160, but, the municipality having admitted it, found that the reasons given breached sections 171 and 2; this alone did not justify annulment.
Provisions applied: section 2, section 24(xxxvi), section 160, section 171Read the decision (Danish)Case 21/10894Partly upheld
Atea A/S v Region Sjælland
The complaint concerned a framework agreement for an indoor mobile coverage system (DAS) for Region Sjælland's hospitals, where the drawings provided were not accurate. The Complaints Board held that the region breached section 2(1) by not neutralising the incumbent's competitive advantage as far as possible and by not publishing an extension of the time limit as a corrigendum to the contract notice, but rejected the claims on a change of fundamental elements and an insufficient extension of the time limit under section 93(4); it annulled the award decision.
Provisions applied: section 2(1), section 24(xxxvii), section 93(3), section 93(4)(i), section 93(4)(ii), section 185(2)Read the decision (Danish)
On this site
Previous section
Section 23 — Defence and security
Next section
Section 25 — Mixed contracts relating solely to services covered by the Act
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.