Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold

Section 83 Negotiated procedure without prior publication

Chapter 7 – Procurement procedures and design contests

The consolidated text in force from 6 February 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

A contracting authority may furthermore use the negotiated procedure without prior publication for new works or services consisting in the repetition of similar services or works, entrusted to the economic operator to which the same contracting authority awarded the original contract, on the following conditions:

(i) The works or services conform to a basic project.

(ii) The original contract was awarded in accordance with a procedure complying with section 55.

(iii) The procurement documents for the original procurement of the basic project referred to in paragraph (i) indicate the extent of possible additional works or services and the conditions under which they will be awarded.

(iv) The possibility of using this procedure is indicated in the original procurement documents. The contracting authority shall take into account the estimated total value of the new works or services when applying section 6.

(v) No more than 3 years have elapsed since the conclusion of the original contract.