Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold
Section 128 Contract notices
Chapter 10 – Publication and transparency
(1) A contracting authority shall use contract notices as a means of calling for competition in all procedures, with the exception of the negotiated procedure without prior publication, cf. sections 80-83.
(2) Contract notices shall contain the information set out in Annex V, Part C, to Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65).
(3) The contract notice shall be drawn up using the standard forms of the European Commission, be sent electronically to the Publications Office of the European Union and be published in accordance with Annex VIII to Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65).
Cross-references
This section refers to
Referred to by
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 128. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 25/00851Partly upheld
Arthrex Danmark A/S v Region Midtjylland, Region Syddanmark og Region Sjælland
The complaint concerned, among other things, a minimum requirement in a joint regional framework agreement for arthroscopy equipment that excluded plastic packaging made of styrene polymers (PS and EPS). The Complaints Board found the requirement objective and proportionate and not an unjustified obstacle to competition under section 40(4), and the place of performance stated in the contract notice compliant with section 128(2), but held that the regions breached section 49(2) by not explaining why lot 2 was not divided further, e.g. geographically; the breach did not lead to annulment, and no financial penalty had been claimed.
Provisions applied: section 2, section 40(4), section 49(1), section 49(2), section 128(2)Read the decision (Danish)Case 22/14549Partly upheld
Konsortiet Abena A/S og Coloplast Danmark A/S v Esbjerg Kommune, Middelfart Kommune, Vejle Kommune, Herning Kommune, Fanø Kommune, Vejen Kommune, Varde Kommune og Billund Kommune
The consortium challenged the municipalities' procurement of a framework agreement for ostomy products. The Complaints Board found that the agreement was for pecuniary interest and thus a public contract subject to procurement under section 24(xxiv), and that the municipalities had breached section 2 by not stating a maximum quantity or value for the framework agreement and by capitalising errors in the price lists contrary to the procurement documents; the claims concerning grounds for exclusion, the quality evaluation and unclear requirements were rejected, and the award decision was annulled.
Provisions applied: section 2, section 24(xxiv), section 56, section 128(2), section 137Read the decision (Danish)Case 23/03361 og 23/03362Partly upheld
Meldgaard Miljø A/S v Afatek A/S
The complaint concerned Afatek's repeated use of the accelerated procedure with a 15-day time limit for receipt of tenders in two open procedures for the disposal of incineration slag, citing limited storage space. The Complaints Board found that the accelerated procedure had been used without justification under section 57(5), that shortening the time limit to 15 days without reasons and the short time limit for evidence of the ESPD information breached section 2, and that the contract notice, contrary to section 2, section 128(2) and section 140(2), did not describe the grounds for exclusion and the suitability criteria; the claim for annulment was not upheld.
Provisions applied: section 2, section 57(1), section 57(2), section 57(4), section 57(5), section 128(2), section 140(2), section 151(1)Read the decision (Danish)Case 21/10232Partly upheld
Inlead ApS v Det Digitale Folkebibliotek
Inlead complained that Det Digitale Folkebibliotek, after publishing a voluntary ex ante transparency notice, had directly awarded Reload a contract for developing a base platform. The Complaints Board found that the contract, as part of a larger project, fell under Part II and that DDF had not proved that the conditions of section 80(3)(ii) (absence of competition for technical reasons) were met, in breach of sections 2 and 6, cf. section 128(1), and annulled the award decision; since DDF had exercised due diligence, the contract was not declared ineffective.
Provisions applied: section 2, section 6(1)(iii), section 80(3)(ii), section 128(1)Read the decision (Danish)Case 22/01867Partly upheld
Netcompany A/S v Arbejdstilsynet
The complaint concerned Arbejdstilsynet's evaluation in a procurement of a framework agreement for development, maintenance and operation of its case-management systems. The Complaints Board held that the price evaluation model did not reflect the expected purchases and was therefore unsuitable to identify the most economically advantageous tender (sections 161 and 2), and that costing the winning tenderer's proposed solution on the basis of another tenderer's estimate was manifestly unreasonable, while rejecting the claims on the qualitative evaluation, the maximum value of the framework agreement and a reservation; it annulled the award decision.
Provisions applied: section 2, section 56, section 128(2), section 128(3), section 160(1), section 160(2), section 161, section 164(1)Read the decision (Danish)Case 21/13160Upheld
Peab Asfalt A/S v Øresundsbro Konsortiet I/S
Peab complained that Øresundsbro Konsortiet had not stated the estimated quantity or value of the services to be provided in the contract notice for a framework agreement for paving works. Referring to the Court of Justice's judgment in Case C-23/20, the Complaints Board found that the requirement also applies to services and that the consortium had breached sections 56 and 128(2) and section 2; it annulled the award decision and stated that there were no special circumstances justifying continuation of the contract under section 185(2).
Provisions applied: section 2, section 56, section 128(2), section 185(2)Read the decision (Danish)Case 19/06361Upheld
Simonsen & Weel A/S v Region Nordjylland og Region Syddanmark
Simonsen & Weel complained that the regions had stated neither the estimated quantity or value of the tube-feeding products to be supplied under a framework agreement in the contract notice, nor a maximum quantity or value in the procurement documents. Following the Court of Justice's answer to the Board's preliminary reference (Case C-23/20), the Complaints Board found breaches of sections 56 and 128(2) and section 2, annulled the award decision and stated that there were no special circumstances justifying continuation of the framework agreement under section 185(2).
Provisions applied: section 2, section 56, section 128(2), section 185(2)Read the decision (Danish)
On this site
Previous section
Section 127 — Prior information notices
Next section
Section 129 — Contract award notices
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.