Consolidated Act No. 448 of 8 May 2025

Section 3

Chapter 2 – Notification and standstill period, etc.

The consolidated text in force from 9 May 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

(1) Where a contracting authority decides to award a contract which is covered by Part II or III of the Public Procurement Act or by the Utilities Directive, the contracting authority may not enter into the contract until a standstill period has expired of

(i) 10 calendar days counted from the day after the day on which the contracting authority sent the notification under section 2(1)(ii) or section 171(1)(iii) of the Public Procurement Act, if the notification was made by electronic means, or

(ii) 15 calendar days counted from the day after the day on which the contracting authority sent the notification under section 2(1)(ii) or section 171(1)(iii) of the Public Procurement Act, if the notification was made by letter.

(2) A contracting authority may fix a longer standstill period than the periods referred to in subsection (1).

(3) Subsections (1) and (2) do not apply if

(i) a contract is awarded by a procurement procedure without prior publication of a contract notice,

(ii) a contract is awarded to a supplier pursuant to a framework agreement with or without reopening of competition,

(iii) a contract is awarded to a supplier within a dynamic purchasing system, or

(iv) the only tenderer concerned is the tenderer to whom the contract is awarded, and there are no candidates concerned.