Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold
Section 57 Open procedure
Chapter 7 – Procurement procedures and design contests
(1) A contracting authority shall fix an adequate time limit for the receipt of tenders, cf. section 93.
(2) The time limit shall be a minimum of 35 days from the day following the dispatch of the contract notice.
(3) Where the contracting authority has used a prior information notice, the minimum time limit is, however, 15 days where
(i) the prior information notice contained all the information required in Annex V, Part B, Section I, to Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ 2014 L 94, p. 65), in so far as that information was available at the time of publication of the prior information notice, and
(ii) the prior information notice was sent for publication not less than 35 days and not more than 12 months before the date of dispatch of the contract notice.
(4) Where the contracting authority accepts that tenders may be submitted by electronic means in accordance with rules issued by the Minister for Industry, Business and Financial Affairs pursuant to section 194(1), the time limit referred to in subsection (2) may be reduced by 5 days.
(5) Where a state of urgency duly substantiated by the contracting authority renders the time limit laid down in subsection (2) impracticable, the contracting authority may fix a time limit which shall not be shorter than 15 days from the day following the dispatch of the contract notice.
(6) The contracting authority shall publish the remaining procurement documents on the date of publication of the contract notice, cf. section 132.
Cross-references
This section refers to
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 57. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 23/07108Not upheld
Oshkosh Airport Products, United States of America v Forsvarsministeriets Materiel- og Indkøbsstyrelse
Oshkosh Airport Products, which did not submit a tender, challenged several technical specifications in Forsvarsministeriets Materiel- og Indkøbsstyrelse's open procedure for crash tenders for military airports, including requirements on width, height, engine and brakes, as well as the time limit for receipt of tenders. The Complaints Board found that the requirements were objectively justified by the contracting authority's needs within its wide discretion under section 40(4) and section 2, and that the time limit complied with the minimum time limit in section 57.
Provisions applied: section 2, section 40(4), section 42, section 57(2), section 57(4), section 93Read the decision (Danish)Case 23/03361 og 23/03362Partly upheld
Meldgaard Miljø A/S v Afatek A/S
The complaint concerned Afatek's repeated use of the accelerated procedure with a 15-day time limit for receipt of tenders in two open procedures for the disposal of incineration slag, citing limited storage space. The Complaints Board found that the accelerated procedure had been used without justification under section 57(5), that shortening the time limit to 15 days without reasons and the short time limit for evidence of the ESPD information breached section 2, and that the contract notice, contrary to section 2, section 128(2) and section 140(2), did not describe the grounds for exclusion and the suitability criteria; the claim for annulment was not upheld.
Provisions applied: section 2, section 57(1), section 57(2), section 57(4), section 57(5), section 128(2), section 140(2), section 151(1)Read the decision (Danish)