Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold

Section 134 Additional information and modifications of the procurement documents

Chapter 10 – Publication and transparency

The consolidated text in force from 6 February 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

(1) A contracting authority may make modifications to the procurement documents where the following requirements are complied with:

(i) The modifications are published in an appropriate manner.

(ii) Notice of the modification is given in compliance with the time limits for additional information, cf. subsections (2) and (3).

(iii) The modifications do not constitute modifications of fundamental elements, cf. section 24(xxxvii).

(2) A contracting authority shall, no later than 6 days before the expiry of the time limit for the submission of requests to participate or tenders, communicate any additional information on the procurement documents and any additional documents, cf. however subsection (3).

(3) In open procedures, restricted procedures and competitive procedures with negotiation under the accelerated procedure, cf. section 57(5), section 59(3), section 60(6), section 63(2), cf. section 59(3), and section 65(2), cf. section 60(6), the contracting authority shall communicate additional information on the procurement documents and any additional documents no later than 4 days before the expiry of the time limit for the submission of requests to participate or tenders.

Decisions of the Complaints Board

Decisions in which the Complaints Board for Public Procurement applied section 134. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.

  • Case 22/14577Partly upheld

    Dustin A/S v Staten og Kommunernes Indkøbsservice A/S

    Dustin challenged several aspects of SKI's procurement of a framework agreement for computers, including an extension of the time limit, modifications of the procurement documents, references to specific makes and the award to Comm2IG. The Complaints Board found that SKI breached section 2 by sending the notice extending the time limit to the EU Publications Office only after the time limit had expired and, by a majority, by awarding both lots to Comm2IG without the check described in the tender conditions although its tenders were non-compliant, and annulled the award decision, while the claims concerning modifications of the procurement documents (sections 93 and 134) and section 42 were rejected.

  • Case 21/07625Not upheld

    Koss ApS v Indkøbsfællesskabet IFIRS

    Koss challenged IFIRS' open procedure for a framework agreement for teaching materials for hairdressing training, including the handling of samples, alleged ambiguities in the procurement documents on course prices and the term «tender sum», and IFIRS' failure to answer a question asked after the time limit for additional information. The Complaints Board found that the procurement documents were sufficiently clear, that IFIRS was not obliged to provide additional information after the time limit where the information appeared from the procurement documents, and that the principles of equal treatment and transparency in section 2 had not been breached.

All decisions by section

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.