Skip to content

Practical guide

Modifying contracts under the Public Procurement Act: when must you re-tender?

A contract or framework agreement that has been tendered cannot be changed freely. This guide explains when a modification requires a new procurement procedure, when it is permitted, and when the contracting authority may terminate the contract.

Updated 23 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 23 November 2026

Legal basissection 178(1) · section 178(2) · section 179(1) · section 180(1) · section 180(2) · section 181(1) · section 181(2) · section 182 · section 183 · section 184(1) · section 184(2) · section 185(1) · section 185(2) · official text

Once a contract has been awarded after a tender, the other tenderers have based their bids on the terms in the procurement documents. If the contracting authority could later change the contract freely, competition could be circumvented in practice. The Public Procurement Act (udbudsloven) therefore limits how far a contract or framework agreement may be modified during its term, and lists the cases in which a modification is permitted without a new procedure.

The main rule: modifying essential elements requires a new procedure

Where essential elements of a contract or framework agreement are modified, the contracting authority must carry out a new procurement procedure (section 178(1) of the Public Procurement Act). A modification is a modification of essential elements where it renders the contract or framework agreement materially different in character from the one originally concluded (section 178(2) of the Public Procurement Act).

The Act lists four cases in which a modification is always regarded as a modification of essential elements, unless one of the exceptions below applies:

The assessment is concrete. The question is always whether the change alters the character of the contract, or whether it is in substance a new contract on which other undertakings could also have bid.

Modifications provided for in the procurement documents (review clauses)

Modifications provided for in the procurement documents in clear, precise and unequivocal clauses are not modifications of essential elements (section 179(1) of the Public Procurement Act). The clauses must state the scope and nature of possible modifications or options and the conditions under which they may be used, and they must not alter the overall nature of the contract or framework agreement. The Act gives as examples price indexation, replacement of communications equipment so that it remains suitable, and addressing technical difficulties arising during operation or maintenance (section 179(2) of the Public Procurement Act).

In practice the contracting authority should think about future change needs before the tender is carried out. A vague clause stating that the authority may change the service "if the need arises" does not meet the requirement of clarity. The clause must describe what can be changed, by how much, and on what conditions.

De minimis: small modifications

A modification is not a modification of essential elements where its value is below both the thresholds in section 6 of the Public Procurement Act and a percentage limit: 10 per cent of the value of the original contract for supplies and services, and 15 per cent for works (section 180(1) of the Public Procurement Act). Both conditions must be met. Where several modifications have been made, their values are added together (section 180(2) of the Public Procurement Act), and the modifications must not alter the overall nature of the contract (section 180(3) of the Public Procurement Act).

Additional supplies from the original contractor

Additional works, services or supplies from the original contractor are permitted where they have become necessary for performance of the contract and a change of contractor cannot be made for economic or technical reasons and would cause significant inconvenience or substantial duplication of costs for the contracting authority (section 181(1) of the Public Procurement Act). The value must not exceed 50 per cent of the value of the original contract (section 181(2) of the Public Procurement Act); where several successive modifications are made, the limit applies to each modification (section 181(3) of the Public Procurement Act).

Replacement of the contractor

Replacement of the original contractor is not a modification of essential elements where it results from a clear, precise and unequivocal review clause or option, or from the contractor's restructuring, for example by takeover, merger, acquisition or insolvency, provided that the original qualitative selection criteria are still met and the replacement neither entails other essential modifications nor is aimed at circumventing the Act (section 182 of the Public Procurement Act).

Unforeseen modifications

Modifications are also not regarded as essential where the need for them could not have been foreseen by a diligent contracting authority, the overall nature of the contract is not altered, and the value of the modification does not exceed 50 per cent of the value of the original contract (section 183 of the Public Procurement Act). All three conditions must be met.

Calculation and notice

Where a contract contains a price indexation clause, the maximum permitted change in value under the various limits is calculated on the basis of the updated price at the time of the modification (section 184(1) of the Public Procurement Act). Where a contract is modified under the rules on additional supplies or unforeseen circumstances, the contracting authority must publish a notice of the modification in the Official Journal of the European Union (section 184(2) of the Public Procurement Act).

Termination of the contract

The contracting authority may terminate a contract or framework agreement in four cases (section 185(1) of the Public Procurement Act):

  • the contract has been substantially modified in a way that would have required a new procurement procedure
  • the contractor was subject to a ground for exclusion at the time of award and should have been excluded
  • the contractor becomes subject to a ground for exclusion during the contract term and cannot demonstrate its reliability
  • the contract should not have been awarded to the contractor because of a serious infringement of the Treaties established by the Court of Justice of the European Union

Where an award decision has been annulled by a final decision or judgment, the contracting authority must as a rule terminate the contract on reasonable notice, unless special circumstances speak in favour of continuing it. A decision to continue the contract must be published in the same place as the procurement documents no later than 7 calendar days after publication of the decision or judgment (section 185(2) of the Public Procurement Act). See complaints and remedies for how the Complaints Board for Public Procurement can declare a contract ineffective.

Putting the rules to use

Always document the assessment before a modification is agreed: which provision it relies on, how the value was calculated, and why the nature of the contract does not change. An unlawful modification can be brought before the Complaints Board for Public Procurement. See also the exemptions from the duty to tender and the procedures.

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.