Framework agreements under the Public Procurement Act: term, direct award and reopening of competition

How a framework agreement is concluded and used: its term, who may use it, and how contracts are awarded by direct award or by reopening competition.

Updated 23 November 2026

Reviewed by Mara Ribeiro Duarte, Head of Public Sector at Closer · 23 November 2026

Legal basissection 24(xxx) · section 95(1) · section 95(2) · section 95(3) · section 96 · section 97 · section 98(1) · section 98(2) · section 98(3) · section 99 · section 100(1) · section 100(2) · section 100(3) · section 129(3) · section 174(2) · official text

A framework agreement is an agreement between one or more contracting authorities and one or more economic operators, which sets the terms governing contracts to be awarded during a given period, in particular as regards price and the quantities envisaged (section 24(xxx) of the Public Procurement Act). Framework agreements suit recurring purchases where the authority does not want to tender each individual order. The rules are in chapter 8 of the Public Procurement Act (udbudsloven).

Conclusion and term

A framework agreement must be concluded under one of the procedures of the Act (section 95(1) of the Public Procurement Act). It is not a shortcut around tendering: the framework itself must be procured under the rules of the procedure chosen.

A framework agreement may have a term of at most 4 years. In exceptional cases it may be concluded for a longer period (section 95(2) of the Public Procurement Act). Contracts based on the framework must be concluded during its term, but they may remain in force for a period after the framework has expired (section 95(3) of the Public Procurement Act).

The contract notice must state which contracting authorities may use the framework, and contracts may be concluded between the parties to the framework (section 96 of the Public Procurement Act).

What the procurement documents must say

The definition of a framework agreement refers to price and envisaged quantities (section 24(xxx) of the Public Procurement Act). The procurement documents should therefore describe the scope of the framework precisely enough for tenderers to price their offers: for example the expected quantity or value, the deliverables and terms covered, and the term. The provisions read contain no express rule that an estimated maximum quantity or value must be stated. The principle of transparency (section 2(1) of the Public Procurement Act) nevertheless points to as clear a description as possible.

The procurement documents must also state how contracts are awarded (section 98(3) of the Public Procurement Act), and the objective criteria for choosing between direct award and reopening of competition (section 98(2) of the Public Procurement Act).

Three ways of using the framework

One supplier. If the framework is concluded with a single winning tenderer, contracts are awarded on the terms laid down in the framework. Before awarding, the authority may ask the supplier in writing to complete its tender (section 97 of the Public Procurement Act).

Several suppliers. If the framework is concluded with more than one party, contracts may be awarded by direct award or by reopening competition (section 98(1) of the Public Procurement Act). The authority may use both under the same framework. The choice must be made on objective criteria, including the quantity, value or characteristics of what is required and the authority's other specific needs, and the criteria must be in the procurement documents (section 98(2) of the Public Procurement Act).

MethodBasisProvision
Direct awardThe terms of the framework and the objective criteria in the procurement documentssection 99 of the Public Procurement Act
Reopening of competitionThe same terms, more precisely formulated where necessary, or other terms laid down in advancesection 100(1) of the Public Procurement Act

Direct award

Direct award is made on the basis of the terms of the framework and the objective criteria laid down in the procurement documents (section 99 of the Public Procurement Act). The authority therefore has no free choice. The mechanism (for example ranking, rotation or particular needs) must be derivable from the procurement documents, so that it is clear in advance who gets which contract. For a direct award the authority need not prepare the individual report (section 174(2) of the Public Procurement Act).

Reopening of competition (mini-competition)

Reopening must be based on the same terms as applied to the award of the framework, more precisely formulated where necessary, or other terms laid down in advance in the procurement documents (section 100(1) of the Public Procurement Act). The authority cannot introduce new requirements along the way.

Competition is reopened by simultaneously inviting in writing the operators capable of performing the contract to submit tenders in writing. The invitation must state the time limit and other necessary information (section 100(2) of the Public Procurement Act). The contract is awarded on the basis of the award criteria laid down in the procurement documents for the framework (section 100(3) of the Public Procurement Act). See the guide on award criteria.

Notification, standstill and notice

No standstill period applies where a contract is awarded under a framework agreement (section 3(3)(ii) of the Complaints Board Act). That does not mean the rules can be set aside: a contract based on a framework with reopening of competition that is concluded in breach of the Act may in certain circumstances be declared ineffective, unless the authority has followed the notification rules and considers that the contract was concluded lawfully (section 17(1)(iii) of the Complaints Board Act, section 17(2) of the Complaints Board Act). The exception presupposes that the authority has followed the rules on notification (section 171(1) of the Public Procurement Act). See the guide on award and standstill.

No later than 30 days after concluding a framework agreement, the authority must send a contract award notice, and notifying the individual contracts based on the framework is optional (section 129(1) of the Public Procurement Act, section 129(3) of the Public Procurement Act).

Practical tips

  • Describe in the procurement documents how contracts are awarded and when competition is reopened. Do not choose according to who is best placed when the need arises.
  • Keep the term to 4 years at most unless there are exceptional circumstances, and document them.
  • Remember that contracts must be concluded while the framework is running.
  • Frameworks can be combined with electronic auctions and catalogues, see the guide on dynamic purchasing systems and auctions.

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.