Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold

Section 178 Modification of contracts, etc.

Chapter 15 – Performance of contracts

The consolidated text in force from 6 February 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

(1) In the event of a modification of essential elements of a contract or framework agreement, the contracting authority shall conduct a new procurement procedure in accordance with this Act.

(2) A modification of a contract or framework agreement is deemed to be a modification of essential elements where it renders the contract or the framework agreement materially different in character from the one initially concluded. Unless otherwise follows from sections 179-183, a modification is always deemed to be a modification of essential elements where

(i) the contracting authority introduces conditions which, had they been part of the initial procurement procedure, would have allowed for the admission of candidates other than those initially selected or for the acceptance of a tender other than that originally accepted or would have attracted additional participants in the procurement procedure,

(ii) the modification changes the economic balance of the contract or the framework agreement in favour of the contractor in a manner which was not provided for in the initial contract or framework agreement,

(iii) the modification considerably extends the scope of the contract or the framework agreement, or

(iv) a new contractor replaces the one to which the contracting authority had initially awarded the contract.

Decisions of the Complaints Board

Decisions in which the Complaints Board for Public Procurement applied section 178. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.

  • Case 24/03446Not upheld

    Mediq Danmark A/S v Staten og Kommunernes Indkøbsservice A/S

    Mediq complained that SKI had awarded a framework agreement for nursing supplies to Abena although Abena's tender was, in Mediq's view, non-compliant, and that by approving the e-catalogue SKI had accepted changes to fundamental elements of the framework agreement. The Complaints Board found that, although the tender was non-compliant on nine product lines, nothing in it gave SKI reason to doubt its accuracy so as to require further checks under sections 159(3) and 164(2), that setting up the e-catalogue after conclusion of the agreement was not a check of the tender's compliance, and that there was no modification contrary to section 178.

  • Case 23/12520Not upheld

    Biogen (Denmark) A/S v Amgros I/S

    Biogen complained that Amgros had awarded Sandoz first priority under a framework agreement for the medicine dimethyl fumarate although, in Biogen's view, Sandoz's supplies would infringe Biogen's patent rights and regulatory data and marketing protection, and that Amgros had not enforced the framework agreement. The Complaints Board found that when the contract was concluded there was no certainty or high probability that Sandoz could not supply, so Amgros was not required to reject the tender under sections 2 and 159(2) and (3), and that Amgros had not modified essential elements of the framework agreement in breach of section 178(1).

  • Case 22/03178Not upheld

    Atea A/S v Udenrigsministeriet

    Atea complained again about the Ministry of Foreign Affairs after an earlier ruling that the winner of a framework agreement did not meet a minimum requirement for certification, arguing that the ministry had waived the requirement and thus modified the framework agreement contrary to section 2(1) and section 178. The Complaints Board found that the ministry had enforced the requirement immediately after the earlier ruling and that the supplier had obtained the certifications within a reasonable time; the claim for annulment of the award decision was dismissed as out of time.

  • Case 20/14737Partly upheld

    Atea A/S v Udenrigsministeriet

    The complaint concerned the Ministry of Foreign Affairs' award of a framework agreement for cabling and access security to a tenderer that did not itself meet a minimum certification requirement. The Complaints Board held that the requirement clearly applied to the supplier itself and could not be met through subcontractors, so the ministry breached section 2(1) by not rejecting the tender, but found that the requirement had not been waived contrary to section 178 and that there was no basis for declaring the contract ineffective; annulment had not been claimed.

  • Case 20/11681Not upheld

    Geelmuyden Kiese A/S v Aarhus Kommune

    Geelmuyden Kiese challenged Aarhus Kommune's award, under Part III of the Public Procurement Act, of a contract to operate the Internet Week Denmark festival, arguing among other things that the winner should have been excluded because a former project manager of the municipality had joined it, that a later modification of the contract was substantial, and that the evaluation was flawed. The Complaints Board found that all relevant information had been made available to all tenderers and no time advantage had materialised, cf. section 39(2)(i) and (ii), that relaxing the requirement of a separate CVR number was not a substantial modification under the principles of section 178, that the winner could tender as a group of economic operators under section 139(2), and that the evaluation was within the municipality's discretion.

All decisions by section

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.