Consolidated Act No. 448 of 8 May 2025
Section 2
Chapter 2 – Notification and standstill period, etc.
(1) Where a contracting authority conducts a procurement procedure which is covered by the Utilities Directive, the contracting authority must notify all candidates and tenderers concerned of the decisions it takes, including, among others, decisions on
(i) the prequalification of undertakings,
(ii) the award of a contract,
(iii) admission to a dynamic purchasing system, and
(iv) the annulment of procurement proceedings.
(2) The contracting authority’s notification of the decision under subsection (1)(ii) must be accompanied by a statement of reasons for the decision. The notification must also state when the standstill period, cf. section 3(1), expires.