Skip to content

Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold

Section 161 Criteria for the award of contracts

Chapter 13 – Procedure for the award of contracts

The consolidated text in force from 6 February 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

A contracting authority shall award the contract to the tenderer that has submitted the most economically advantageous tender.

Cross-references

Decisions of the Complaints Board

Decisions in which the Complaints Board for Public Procurement applied section 161. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.

  • Case 25/06148Not upheld

    CGI Danmark A/S v Erhvervsstyrelsen

    CGI challenged the price evaluation model Erhvervsstyrelsen used in a mini-competition under a framework agreement, arguing that it did not reflect expected costs because the split between on-site and off-site consultants could change during the contract. The Complaints Board found that this possibility did not in itself make the model unsuitable for identifying the most economically advantageous tender under section 161, and that the model was transparent and complied with equal treatment under section 2.

  • Case 23/00727Upheld

    De Forenede Dampvaskerier A/S v Odense Kommune

    DFD challenged Odense Kommune's award of a contract for the washing and rental of cloths and mops. As the municipality admitted that it had infringed section 2(1), section 161 and section 162(1) by awarding the contract to a tenderer that had not submitted the most economically advantageous tender on the basis of the award criterion laid down, and by setting unclear conditions for the basis of tendering, the Complaints Board upheld the claims and annulled the award decision.

  • Case 22/01867Partly upheld

    Netcompany A/S v Arbejdstilsynet

    The complaint concerned Arbejdstilsynet's evaluation in a procurement of a framework agreement for development, maintenance and operation of its case-management systems. The Complaints Board held that the price evaluation model did not reflect the expected purchases and was therefore unsuitable to identify the most economically advantageous tender (sections 161 and 2), and that costing the winning tenderer's proposed solution on the basis of another tenderer's estimate was manifestly unreasonable, while rejecting the claims on the qualitative evaluation, the maximum value of the framework agreement and a reservation; it annulled the award decision.

All decisions by section

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo