Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold
Section 81 Negotiated procedure without prior publication
Chapter 7 – Procurement procedures and design contests
(1) A contracting authority may furthermore use the negotiated procedure without prior publication for public supply contracts and public service contracts, as regards paragraph (iv),
(i) where the supplies concerned are manufactured purely for the purpose of research, experiment, study or development, and contracts awarded under this provision do not include quantity production to establish commercial viability or to recover research and development costs,
(ii) for additional deliveries by the original supplier which are intended either as a partial replacement of supplies or installations or as the extension of existing supplies or installations, where a change of supplier would oblige the contracting authority to acquire supplies having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance,
(iii) for supplies quoted and purchased on a commodity market, and
(iv) for the purchase of supplies or services on particularly advantageous terms, from either a supplier which is definitively winding up its business activities, or the liquidators in an insolvency procedure, an arrangement with creditors, or a similar procedure under national laws and regulations.
(2) The duration of contracts covered by subsection (1)(ii) may, as a general rule, not exceed 3 years.
Cross-references
Previous section
Section 80 — Negotiated procedure without prior publication
Next section
Section 82 — Negotiated procedure without prior publication