Skip to content

Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold

Section 80 Negotiated procedure without prior publication

Chapter 7 – Procurement procedures and design contests

The consolidated text in force from 6 February 2025, as published in Retsinformation. Where this page and the official text differ, the official text prevails: official textThis English text is Procurelex’s unofficial translation, not yet reviewed by a lawyer. Only the Danish text published on Retsinformation is authentic. Read the Danish text on this site or on Retsinformation.

(1) A contracting authority may use the negotiated procedure without prior publication where, in connection with an open or restricted procedure for public works contracts, public supply contracts and public service contracts,

(i) no requests to participate or tenders have been received, or

(ii) only requests to participate or tenders that are irrelevant to the contract have been received.

(2) It is a condition under subsection (1) that the fundamental elements of the original procurement documents are not substantially altered and that a report is sent to the European Commission if it so requests.

(3) A contracting authority may also use the negotiated procedure without prior publication where the works, supplies or services can be supplied only by a particular economic operator for any of the following reasons:

(i) the aim of the procurement is the creation or acquisition of a unique work of art or artistic performance,

(ii) absence of competition for technical reasons, or

(iii) the protection of exclusive rights, including intellectual property rights.

(4) Paragraphs (ii) and (iii) of subsection (3) apply only where no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters of the procurement.

(5) A contracting authority may also use the negotiated procedure without prior publication, in so far as is strictly necessary, where, for reasons of extreme urgency brought about by events unforeseeable by the contracting authority, the time limits for open procedures, restricted procedures or competitive procedures with negotiation cannot be complied with.

Decisions of the Complaints Board

Decisions in which the Complaints Board for Public Procurement applied section 80. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.

  • Case 24/10982Partly upheld

    Zeppelin Danmark A/S v Forsvarsministeriets Materiel- og Indkøbsstyrelse

    Zeppelin challenged FMI's switch, after an open procedure in which no tenders were received, to a negotiated procedure without prior publication ending in a framework agreement for wheel loaders with Volvo. The Complaints Board found the switch lawful under section 80(1)(i) and the length of the negotiations not disproportionate, but held that FMI had changed fundamental elements contrary to section 80(2) by accepting a model that did not meet the minimum requirements and by changing the price structure; the framework agreement was declared ineffective and a financial penalty imposed.

  • Case 23/05915Partly upheld

    Acapulka AS v Forsvarsministeriets Materiel- og Indkøbsstyrelse

    Acapulka complained that FMI had bought sledges (pulks) directly from another supplier without any procurement procedure. The Complaints Board found that the purchase was not covered by the defence and security directive, that the conditions for extreme urgency in section 80(5) were not met, and that the contract was below the threshold in section 6(2) but of clear cross-border interest, so FMI had breached section 2 read with section 191(1) and section 192(1) and (2); the decision to conclude the contract was annulled.

  • Case 22/14569Partly upheld

    SundVikar A/S v Fællesindkøb Fyn v/Faaborg-Midtfyn Kommune

    SundVikar complained that Fællesindkøb Fyn had concluded a temporary framework agreement for temporary staffing services with Carelink without prior publication of a contract notice after SKI had terminated its framework agreement with SundVikar. The Complaints Board found that the conditions of section 187(5), cf. section 80(5), were not met, since the termination was not unforeseeable and extreme urgency had not been shown; as the framework agreement had expired, it could not be declared ineffective, and a financial penalty of DKK 400,000 was imposed instead.

  • Case 22/14561Not upheld

    DiaLab, Dansk Diagnostika- og Laboratorieforening v Region Midtjylland

    The complaint concerned Region Midtjylland's direct award of contracts for antigen self-tests in 2021 during the COVID-19 epidemic on the basis of section 80(5). The Complaints Board found that the region had shown that the cumulative conditions were met: the need was unforeseeable, extreme urgency made it impossible to make the purchases through a procedure under section 55, including an accelerated procedure, or through the dynamic purchasing system, there was a causal link, and the purchases were limited to what was strictly necessary.

  • Case 21/10232Partly upheld

    Inlead ApS v Det Digitale Folkebibliotek

    Inlead complained that Det Digitale Folkebibliotek, after publishing a voluntary ex ante transparency notice, had directly awarded Reload a contract for developing a base platform. The Complaints Board found that the contract, as part of a larger project, fell under Part II and that DDF had not proved that the conditions of section 80(3)(ii) (absence of competition for technical reasons) were met, in breach of sections 2 and 6, cf. section 128(1), and annulled the award decision; since DDF had exercised due diligence, the contract was not declared ineffective.

  • Case 19/07906Partly upheld

    Remondis A/S v Silkeborg Genbrug og Affald A/S

    Remondis complained that Silkeborg Genbrug og Affald had awarded HCS a temporary waste collection contract without a procurement procedure after Remondis had terminated its contract and two procurements had been cancelled because of errors. The Complaints Board found that SGA had not proved that the conditions for extreme urgency in section 80(5) were met, since it had had enough time to carry out a lawful procedure, so it had breached sections 2 and 6; the award decision was annulled, but the contract was maintained for overriding reasons of general interest.

All decisions by section

Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.